LEELA AASHISH

P51800005141 · promoter Leela Creators

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51800005141
Registered on09 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Leela Creators is the promoter of record on 82 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
LEELA AASHISH1G+9-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by MCGM ROAD, to the south by R G PLOT, to the east by KEDARMAL ROAD and to the west by PLOT. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad East

DEM Phoenix
possession by Jul 2026 · DEM Buildwell
Rajhans Solitaire
possession by Aug 2026 · Rajhans Residency
Amann Highland Park
possession by Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
possession by Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd

Other RERA-registered projects in Mumbai Suburban

Leela Business Park - II
possession by Dec 2029 · Rockfort Estate Developers Private Limit
Leela Sterling
declared completion Dec 2023 · Vora Estate Developers
Leelas Residency
declared completion Dec 2025 · OM Navkaar Developers
Legacy
possession by Jun 2029 · Ashirwad Nice Developers
Legranz
declared completion Dec 2019 · Ekta Shubham Venture
Lekh Residency
possession by Dec 2026 · Lekh Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026