MahaRERA Property Intelligence · Mumbai Suburban

MAKHDOOMI PALACE

P51800009033 · Kolekalyan Santacruz East · promoter Dolphin Developers

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51800009033
Registered on19 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Dolphin Developers is the promoter of record on 18 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
makhdoomi1G+1230 Dec 2023

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000020940316/12/2021Mrs. Eliza D'souza vs M/s Dolphin Developersorder passed
CC00600000025191416/07/2022Francis Charlie D'souza vs M/s. Dolphin Developersorder passed

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 5 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Dindoshi City Civil Court13912013Pending
Dindoshi City Civil Court26722013Pending
Dindoshi City Civil Court7022014Pending
Dindoshi City Civil Court29352015Pending
Dindoshi City Civil Court15372015Pending

Location, Land & Connectivity

Located at Kolekalyan Santacruz East, Santacruz, Andheri, Mumbai Suburban, 400055. Per the filed land record, the plot is bounded to the north by ST ANTHONY ROAD, to the south by HABIB MANZIL, to the east by VAKOLA MASJID LANE and to the west by VICTORY HOUSE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport1 km
Bandra Kurla Complex (BKC)2 km
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dolphin Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Dolphin Developers

Dolphin Developers
FlaggedRaigarh
Dolphin Developers
FlaggedRaigarh
Dolphin Developers
FlaggedRaigarh
Dolphin Developers
FlaggedRaigarh
Dolphin Developers
FlaggedRaigarh

Other RERA-registered projects in Santacruz East

Pruthi Annexe
possession by Sep 2026 · Raja Developers
Crystal Avenue
possession by Nov 2026 · Eternia Realty
Vaibhav Heights
possession by Dec 2026 · RSN Balaji Realtors P LTD
Ambit Vista
possession by Dec 2026 · Ambit Builders & Developers
Atmiya Centria
possession by Dec 2026 · Upturn Properties LLP
Crescent Nexus
possession by Dec 2026 · Ascent Infraspace Private Limited

Major developers building in Santacruz East

Other RERA-registered projects in Mumbai Suburban

Malad Amar CO-Operative Housing Socity LTD
possession by Dec 2026 · Ardhya Universal LLP
Malad Babel CHS LTD
declared completion Oct 2020 · Siscorn Developers
Malad Rajesh Park CHS LTD
declared completion Dec 2025 · MS Developers
Malad Sati Darshan CHS Ltd
declared completion May 2026 · Goyal Sati Darshan LLP
Malad Shaligram
declared completion Mar 2025 · Stans Buildtech Realtors
Malad Shanti
declared completion Oct 2020 · Sachit Thakkar

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026