MAYUR PHASE II 16TH TO 19TH FLOOR

Mumbai Suburban · Geopreneur Spire Realty

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010897

Delivery and registration

When is the project declared for completion?

MAYUR PHASE II 16TH TO 19TH FLOOR is registered with MahaRERA as P51800010897 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010897
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAYUR PHASE II 16TH TO 19TH FLOOR record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Geopreneur Spire Realty is the promoter of record on 4 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAYUR PHASE II 16TH TO 19TH FLOOR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
MAYUR PHASE II WING A1G+6-
MAYUR PHASE II WING B1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KHER NAGAR BUILDING NO 17, Borivali, Mumbai Suburban, 400051. Per the filed land record, the plot is bounded to the north by 12-20 M EXISTING ROAD, to the south by EXISTING BUILDING 31, to the east by EXISTING BUILDING NO 16 and to the west by EXISTING BUILDING 18. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Lower Parel / Worli business district7 km
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park8 km
Nariman Point / Fort15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Geopreneur Spire Realty is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Geopreneur Spire Realty

Geopreneur Spire Realty
FlaggedMumbai Suburban

Other RERA-registered projects in Bandra East

A And O Estado
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Builders AND Developers
Antariksh Ace
possession by Dec 2026 · Pittie Antariksh Realty Private Limited
Bandra North Gulmohar Avenue
possession by Dec 2026 · Shivalik Ventures Private Limited
Gurukrupa Nirmalam
possession by Dec 2026 · Gurukrupa Realcon Infrastructure LLP
LEO Eminence
possession by Dec 2026 · LEO Infrastructure Private Limited
Mayur Tower
possession by Dec 2026 · Geopreneur Spire Realty

Major developers building in Bandra East

Other RERA-registered projects in Mumbai Suburban

Mayur Tower
possession by Dec 2026 · Geopreneur Spire Realty
MDM Maestro
possession by Dec 2026 · MDM Realty LLP
Meadows 83
possession by Oct 2026 · Shreeji Realtors
Medinee CHS Ltd
declared completion Sep 2018 · Shamik Enterprises Pvt Ltd.
Medinee Niketan
declared completion Dec 2023 · SS Enterprise
Mediterranean
possession by Mar 2027 · Fortune Investments

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026