Mumbai/Project record

MahaRERA · the public record

Moosa Residency

Navare Nagar · M S Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700023083

Delivery and registration

When is the project declared for completion?

Moosa Residency is registered with MahaRERA as P51700023083 and the promoter has declared completion for 31 May 2024.

31 May 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700023083
Registered on29 Nov 2019
Promoter-declared completion31 May 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Moosa Residency record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Moosa Residency in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Moosa Residency1G+631 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 May 2024Dear Sir, this is to bring to your notice that our project is delayed due to the various reason for eg. Covid 19, lack of funds, delay in material, we had faced many difficulties d

Location, Land & Connectivity

Located at Navare Nagar, Kalyan-Badlapur Road, Ambarnath, Thane, 421506. Per the filed land record, the plot is bounded to the north by S No 121 H No 3, to the south by S No 121 H No 3, to the east by S No 121 H No 4 and S No 121 H No 11 and to the west by Existing Road Four and Half metres wide. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M S Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Ambarnath

Empire Industrial Centrum Phase 6
Deregistered by MahaRERA · possession by Oct 2026 · Empire Industries LTD
Empire Industrial Centrum Phase 5
possession by Jun 2027 · Empire Industries LTD
MID-Town
possession by Jun 2028 · Siddhivinayak Group NX
Precious Infinity
possession by Dec 2028 · RKR Construction
Tharwanis Meghna Montana Phase - 3
possession by Dec 2028 · Tharwani Constructions PVT LTD
Sai Prasad Apartment
possession by Apr 2029 · Not Available

Other RERA-registered projects in Thane

Moraj Silent Valley
possession by Apr 2030 · Moraj Buildcon PVT LTD
Moreshwar Nagar II
declared completion Dec 2021 · Siddhivinayak Builders AND Developers
Morivali Ambernath Brondesbury CO-OP Hsg. Society Limited
declared completion Mar 2022 · Morivali Ambernath Brondesbusry CO-OP Hs
Morivali Ambernath Wembley Park CHS LTD
possession by Nov 2028 · Shree Khodiyar Buildcon
Morya Aarambh
declared completion Dec 2023 · Morya Developers
Morya Enclave
possession by Jul 2029 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026