MahaRERA Property Intelligence · Thane

NAVARE PLAZA

P51700020680 · KALYAN EAST · promoter Om Developers

Certificate SignedDue 28 Aug 2022

Delivery & Registration

MahaRERA registrationP51700020680
Registered on03 May 2019
Promoter-declared completion28 Aug 2022
Current statusCertificate Signed
Against todayabout 47 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A WING1G+531 Aug 2021
B WING1G+631 Aug 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Aug 202228 Aug 2023DUE TO COVID 19 THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

Location, Land & Connectivity

Located at KALYAN EAST, MAIN ROAD, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by CTS NO 8035, to the south by 18 MTR WIDE DP ROAD, to the east by CTS NO 7999 and to the west by 9 MTR WIDE DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

OM Developers is the promoter on 26 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every OM Developers project & its RERA track record →

Other flagged projects by OM Developers

OM Developers
FlaggedMumbai Suburban
OM Developers
Past its declared completion dateThane

Other RERA-registered projects in Kalyan

Tharwani Solitaire Phase IV
possession by Jul 2026 · Anil Hardasmal Tharwani
Kailash Gardens
possession by Jul 2026 · Shree Laxmi Enterprises
Mangeshi Ambar
possession by Jul 2026 · Mangesh Dashrath Gaikar
Mangeshi Tulip
possession by Jul 2026 · Mangesh Dashrath Gaikar
Anand 21 Uptown
possession by Aug 2026 · VPA Developers
Pawan Atharva Phase I
possession by Aug 2026 · Pawan Real Estate

Major developers building in Kalyan

Other RERA-registered projects in Thane

Navare Residency And Library
declared completion Dec 2022 · Shree Ganesh Developers
Navjeevan Co-Op. Housing Society Ltd
declared completion Dec 2020 · Avishkar Group
Navkamal Pushpa CHS
declared completion May 2026 · Dream Realtors
Navkar Avenue
declared completion Dec 2025 · Navkar Enterprises
Navkar Bahar
possession by Dec 2026 · AMI Enterprises
Navkar Heights
declared completion Apr 2026 · Rajendra Enterprise

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026