MahaRERA Property Intelligence · Thane
P51700030709 · DOMBIVLI WEST · promoter Ami Enterprises
| MahaRERA registration | P51700030709 |
| Registered on | 08 Sep 2021 |
| Promoter-declared completion | 31 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 5 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~93.7% of the estimated project cost incurred as of the last certificate (₹13.35 Cr spent against a ₹14.25 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 103 homes filed with MahaRERA, 43 are sold/booked and 60 remain available (~42% sold) — selling steadily. Buyers have committed ₹10.80 Cr in agreement value so far. Of that, ₹10.01 Cr (~93%) is already collected, ₹79.32 Lakh receivable — a read on how far along these sales really are. Note: the project registers 144 homes in total, but this sold/unsold inventory filing covers only 103 of them — the other 41 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 43 registered agreements, the effective carpet rate is ₹14,060/sqft (typical range ₹3,920–₹24,746) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 144 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| BUILDING No 2 | 1 | G+8 | 144 | 31 Dec 2025 |
| BUILDING No 2 | 1 | G+8 | - | - |
Unit mix on the filing: 61 residential and 83 non-residential (shops/offices).
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Dec 2025 | 31 Dec 2026 | We have received a Part Occupancy Certificate (OC) for the building from the ground floor up to the fourth floor. The Full Occupancy Certificate is currently awaited from the compe |
Located at DOMBIVLI WEST, DOMBIVLI, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by AS PER REVENUE RECORD, to the south by AS PER REVENUE RECORD, to the east by AS PER REVENIE RECORD and to the west by AS PER REVENUE REORD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 22 km |
| Andheri MIDC / SEEPZ | 24 km |
| Chhatrapati Shivaji Int'l Airport | 27 km |
| Bandra Kurla Complex (BKC) | 28 km |
| Lower Parel / Worli business district | 36 km |
| Nariman Point / Fort | 42 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Free · Watch this project
We'll email you when this project's RERA record changes.
AMI Enterprises is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026