Mumbai/Project record

MahaRERA · the public record

NAVSARTHAK CO-OP HSG SOC LTD

AMBERNATH · V. R. BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700047946

Delivery and registration

When is the project declared for completion?

NAVSARTHAK CO-OP HSG SOC LTD is registered with MahaRERA as P51700047946 and the promoter has declared completion for 31 May 2025.

31 May 2025

declared completion

16months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700047946
Registered on01 Dec 2022
Promoter-declared completion31 May 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NAVSARTHAK CO-OP HSG SOC LTD record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NAVSARTHAK CO-OP HSG SOC LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
NAVSARTHAK CO-OP HSG SOC LTD1G+731 Mar 2025

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for NAVSARTHAK CO-OP HSG SOC LTD, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260238022/04/2026Mahesh Panchal vs V. R. BUILDERSpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 May 2025DELAY IN PROJECT

Location, Land & Connectivity

Located at AMBERNATH , VILLAGE MORIVALI, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by 9 MTR ROAD, to the south by CLASSIC BUILDING, to the east by 18 MTR DP ROAD and to the west by RAGHUNATH PUJA BUILDING. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

V. R. Builders is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Navyug Co.op.hsg.limited
possession by Dec 2026 · Aaradhana Builders AND Developers LLP
Nayan Apartment
declared completion Jul 2022 · Nanda Santosh Bhoir
Nazir Heights
possession by Sep 2026 · A M Constructions
NB Aarambh Residency
declared completion May 2026 · NB Associates Private Limited
Neel Kamal
possession by Jan 2031 · Vividha Realtors Private Limited
Neel Sagar CHS
possession by Dec 2027 · Raju Shantaram Mandavkar

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026