MahaRERA Property Intelligence · Mumbai Suburban

NEW BHAGYASHREE CHS LTD

P51800011529 · promoter Anand Construction Private

Certificate SignedDue 28 Feb 2018

Delivery & Registration

MahaRERA registrationP51800011529
Registered on31 Aug 2017
Promoter-declared completion28 Feb 2018
Current statusCertificate Signed
Against todayabout 101 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
NEW BHAGYASHREE CHS LTD1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201728 Feb 2018Extension Required Till OC Date

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by PLOT NO 42, to the south by PLOT NO 44, to the east by PLOT NO 33 and to the west by LOKMANYA TILAK ROAD NO 3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

New Brindavan Chsl
possession by Dec 2029 · Shree Mahavir Estates
New Deepali Co-Op. Housing Society Ltd
declared completion Mar 2025 · Akme Properties
NEW Ekta CHS
declared completion Dec 2021 · Aditya Developers
NEW Ekta Chsl
possession by Mar 2029 · Shrimad Realtors LLP
NEW Friends SRA CHS LTD
declared completion Oct 2023 · M/s. Viraj Enterpries
NEW Gayatri Darshan CHS
possession by Dec 2027 · Shiv Siddhi Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026