NEW SANTACRUZ SUCHIT CO OPERATIVE HOUSING SOCIETY LTD.

Mumbai Suburban · SHASTRIJI DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800003904

Delivery and registration

When is the project declared for completion?

NEW SANTACRUZ SUCHIT CO OPERATIVE HOUSING SOCIETY LTD. is registered with MahaRERA as P51800003904 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800003904
Registered on06 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEW SANTACRUZ SUCHIT CO OPERATIVE HOUSING SOCIETY LTD. record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEW SANTACRUZ SUCHIT CO OPERATIVE HOUSING SOCIETY LTD. in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
NEW SANTACURZ SUCHIT CO OPERATIVE HOUSING SOCIETY LTD1G+12-

Legal and disputes

What disputes are disclosed?

9 complaints are on the MahaRERA record for NEW SANTACRUZ SUCHIT CO OPERATIVE HOUSING SOCIETY LTD., with orders passed in 8 of them.

9complaints

8with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000040015/05/2021Pankaj H. Sompura vs Bina R. Chawdaorder passed
CC00600000000194923/11/2017CHANDRAKANT SHAH vs RAMNIKBHAI M CHAWADAorder passed
CC00600000005565804/08/2018Mr. Srawan Kumar Killa (HUF) (Nikhil Srawan Killa-Karta) vs M/s. Shastriji Developers LLPorder passed
CC00600000005595226/08/2018KARUNA RAMESHKUMAR SOLANKI AND CHETAN RAMESHKUMAR SOLANKI vs SHASTRIJI DEVELOPERS LLPorder passed
CC00600000007859422/03/2019SANDEEP JAYANTILAL GALA vs SHASTRIJI DEVELOPERS LLPorder passed
CC00600000007907929/04/2019MS. ADITI SHANTARAM KHAIRE vs SHASTRIJI DEVELOPERSorder passed
CC00600000008982422/06/2019Suchit Welfare Association vs Shastriji Develpers LLPorder passed
CC00600000011065905/09/2019Rita Shantaram Khaire vs Bina Ramniklal Chawdaorder passed
CC1260256502/05/2026Pratim Thakur vs SHASTRIJI DEVELOPERS LLPpending / no order on file

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400055. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by CTS NO 3990, to the east by CTS NO 4001 TO 4012 and to the west by CTS NO 3981. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Bandra Kurla Complex (BKC)3 km
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz East

Pruthi Annexe
possession by Sep 2026 · Raja Developers
Crystal Avenue
possession by Nov 2026 · Eternia Realty
Vaibhav Heights
possession by Dec 2026 · RSN Balaji Realtors P LTD
Ambit Vista
possession by Dec 2026 · Ambit Builders & Developers
Atmiya Centria
possession by Dec 2026 · Upturn Properties LLP
Crescent Nexus
possession by Dec 2026 · Ascent Infraspace Private Limited

Other RERA-registered projects in Mumbai Suburban

NEW Shelter CO OP Housing Society LTD
declared completion Dec 2025 · Kaavish Shelter LLP
New Shiv Krupa Chsl Triveni Contour
declared completion Dec 2023 · Triveni Developers
NEW Siddharth CO-Operative Housing Society LTD
possession by Dec 2026 · Not Available
NEW Simit Apartment
declared completion Dec 2024 · Reliable Buildhights LLP
NEW Tashkent Terrace Chsl
declared completion Oct 2018 · Amar Associates
Nicco Kamlesh - Wing C
possession by Dec 2028 · NEW India Construction Company

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026