30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800019863

Delivery and registration

When is the project declared for completion?

Nishchay Wing A is registered with MahaRERA as P51800019863 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800019863
Registered on07 Mar 2019
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Nishchay Wing A record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shreeraj Developer Llp is the promoter of record on 8 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Nishchay Wing A in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+41.

BuildingWingsFloorsDeclared completion
NISHCHAY WING A1G+41-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Nishchay Wing A, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019890702/11/2021Shreeraj Developer LLP vs Shrikant Anand Manjrekarorder passed
CC00600000020940614/12/2021Shreeraj Developer LLP vs Mukesh BHanwarlal Jainorder passed
CC00600000020940714/12/2021Shreeraj Developer LLP vs Falguni Bharat Gor and Bharat Chatrabhuj Gororder passed

Location, Land & Connectivity

Located at Dahisar, S V Road, Andheri, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by CTS 1781 and 1782, to the south by CTS 1785 and 1783, to the east by CTS 1782 and 1779 and to the west by CTS 1781 and 1785. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreeraj Developer LLP is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Dahisar East

Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li
Jeandveekedarnath
possession by Dec 2026 · JE AND VEE Infrastructure
Shri Upendra Chsl
possession by Dec 2026 · Harshal Enterprises
Swayam Niketan
possession by Dec 2026 · Jainam Associates
A And O Eminente
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Housing Private Limited

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

Nityanand Nagar Vibhag IV Cooperative Housing Society Limited
possession by Jun 2027 · Bajaj International Realty Private Limit
Nivara
possession by Mar 2030 · Ara Realty LLP
Nivetia Heights
possession by Jun 2027 · KBS Properties Pvt Ltd
NL Park View
possession by May 2028 · Beautiful Properties Private Limited
Noble Heights
declared completion Dec 2025 · Noble Infra Projects
Noori Horizon
possession by Dec 2029 · Armee Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026