Mumbai/Project record

MahaRERA · the public record

OM SHREE ASHTAVINAYAK COMPLEX,BUILDING NO.2,H,I,J WING

Nr. Moregaon Talav · ASSETS INFRASTRUCTURES CO

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000010145

Delivery and registration

When is the project declared for completion?

OM SHREE ASHTAVINAYAK COMPLEX,BUILDING NO.2,H,I,J WING is registered with MahaRERA as P99000010145 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000010145
Registered on24 Aug 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OM SHREE ASHTAVINAYAK COMPLEX,BUILDING NO.2,H,I,J WING record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Assets Infrastructures is the promoter of record on 12 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OM SHREE ASHTAVINAYAK COMPLEX,BUILDING NO.2,H,I,J WING in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
WING I - BHALCHANDRA1G+1431 Mar 2020
WING J - DHUMRAVARNA1G+1431 Mar 2020
WING H - GAJVAKRA1G+1431 Mar 2020

Legal and disputes

What disputes are disclosed?

9 complaints are on the MahaRERA record for OM SHREE ASHTAVINAYAK COMPLEX,BUILDING NO.2,H,I,J WING, with orders passed in 7 of them.

9complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000029236520/08/2022Sanjay Dighe vs Assets Infrastrutures Co.order passed
CC00600000039654104/07/2023VIDYUT VISHWAS GORE vs M/s ASSETS INFRASTRUCTURE CO. THROUGH ITS PARTNER MR.JATIN C. MODIorder passed
CC00600000039716721/08/2023Pramod Pathak vs Mr Jatin Modiorder passed
CC00600000048001228/04/2024Sandhya Siddhant Singh vs M/s. Assets Infrastructure Co.order passed
CC00600000048001428/04/2024Priyanka Maan Singh vs M/s. Assets Infrastructures Co.order passed
CC1260111001/03/2026Pramod P Pathak vs ASSETS INFRASTRUCTURES COpending / no order on file
CC1260235021/04/2026ASSETS INFRASTRUCTURES CO vs Sandhya Siddhant Singhorder passed
CC1260235121/04/2026ASSETS INFRASTRUCTURES CO vs Priyanka Maan Singhorder passed
CC1260438014/07/2026Vidyut Vishwas Gore vs ASSETS INFRASTRUCTURES COpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2021Due to unavoidable circumstances, the construction of the “OM SHREE ASHTAVINAYAK PHASE II” has to be postponed due to heavy rains in the project site area and surroundings due to w
31 Mar 202130 Sep 20223. Due to nation-wide Covid-19 restrictions and lockdown, there were acute shortage of workers for completion of project. 4. Also, the approval for the construction of additional
30 Sep 202230 Sep 2023The approval for the construction of additional floors (G+10 to G+14) in Wing J which was made to the VVCMC in March 2019 is received now and the same will require additional time

Location, Land & Connectivity

Located at Nr. Moregaon Talav, 126 Nallasopra Link Road, Borivali, Mumbai Suburban, 401209. Per the filed land record, the plot is bounded to the north by SURVEY NO 81 82, to the south by RAJIV GANDHI SCHOOL AND THAKUR VIDYAMANDIR SCHOOL, to the east by BMC Hospital Moregao Talav and to the west by SURVEY NO 52 SAI PARIZAT BLDG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ31 km
Powai / Hiranandani business park33 km
Chhatrapati Shivaji Int'l Airport35 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district45 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara East

Model Cooperative Housing Society LTD
possession by Oct 2026 · Sai Vaishnav Infra Llp
N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
possession by Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
possession by Dec 2026 · MAA Guru Construction
Imperialparamount
possession by Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
possession by Dec 2026 · Blue OAK Infrastructure

Other RERA-registered projects in Palghar

OM Shreeji Darshan CO Operative Housing Society LTD
possession by May 2027 · Jaiprakash Sharamansingh Chauhan
OM Sunkulan
possession by Dec 2028 · Vidhi Enterprises
OM Vighnaharta Tower
declared completion Dec 2025 · OM Vighnaharta Developers
Omkar Apartment
declared completion May 2024 · OM Builders AND Developers
Omkar Apartment
declared completion Dec 2023 · Ravindra Rajesh Kanna
Omkar Palace
declared completion Sep 2021 · Neelam Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026