MahaRERA Property Intelligence · Thane

OMKAR PLAZA D AND E WING

PM1331012600352 · BADLAPUR · promoter Omkar Enterprises

Certificate SignedDue 30 Jun 2027

Delivery & Registration

MahaRERA registrationPM1331012600352
Registered on06 May 2026
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today11 months to the declared date

Builder Track Record

Across MahaRERA, Omkar Enterprises is the promoter of record on 151 projects, of which 21 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 58 homes filed with MahaRERA, 0 are sold/booked and 58 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Note: the project registers 98 homes in total, but this sold/unsold inventory filing covers only 58 of them — the other 40 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 98 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
OMKAR PLAZA CO-OP HOUSING SOCIETY LIMITED 1G+863-
OMKAR PLAZA CO-OP HOUSING SOCIETY LIMITED-G+835-

Unit mix on the filing: 82 residential and 16 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BADLAPUR, 31/3/A PLOT A & PLOT B , 32/1/A/1 PLOT NO. 1,32/1/A/2 PLOT NO. 2, 32/1/A/3 PLOT NO. 3, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by S.NO. 32/1/A/4, to the south by AMBARNATH BADLAPUR ROAD ( 30 M.W. ROAD), to the east by S.NO. 32 and to the west by S.NO. 32/1/A/14. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park35 km
Andheri MIDC / SEEPZ38 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district46 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Omkar Enterprises is the promoter on 15 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Omkar Enterprises project & its RERA track record →

Other flagged projects by Omkar Enterprises

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Omkar Pride
possession by Dec 2029 · Omkar Infrastructure
Omkar Regency
possession by Nov 2028 · Aarav Realtors
Omkar Residency
declared completion Jun 2022 · Pinnacle Lifespaces
Omkar Residency
declared completion Dec 2025 · M/s Omkar Associates
Omkar Residency A-Wing
possession by Dec 2026 · K K Group
Omkar Srushti
possession by Jun 2028 · M/s Omkar Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026