MahaRERA · the public record
One Marina
Chira Bazar Chandanwadi · VALENCIA AND MISHAL VENTURES PVT LTD
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Dec 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51900019619
Delivery and registration
When is the project declared for completion?
One Marina is registered with MahaRERA as P51900019619 and the promoter has declared completion for 30 Dec 2028.
30 Dec 2028
declared completion
27months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51900019619 |
| Registered on | 14 Feb 2019 |
| Promoter-declared completion | 30 Dec 2028 |
| Current status | Certificate Signed |
| Against today | 27 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for One Marina record 29 quarterly progress reports since registration.
29quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In One Marina, ₹136.77 Cr of a declared ₹612.48 Cr estimated project cost is reported as incurred, about 22.3%, as at the last certified filing with MahaRERA.
22.3%
₹136.77 Cr
of ₹612.48 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In One Marina, 187 of 318 homes filed with MahaRERA are recorded as sold or booked (122 with registered agreements and 65 booked), about 59%, and 131 remain available.
59%sold
187 of 318 homes
₹1001.98 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹276.87 Cr (about 28%) is recorded as collected and ₹725.11 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 187 registered agreements, the effective carpet rate is ₹47,994/sqft, with eight in ten falling between ₹31,517 and ₹55,770 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 17 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 187 homes carry one, and 131 of the 318 are recorded unsold. Since we started watching this ledger, 5 homes have moved out of the unsold list, most recently on 08 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 4601 | 902 sqft | Rs 42,621 a sq ft typical, over Rs 0 to Rs 64,992 | 48 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In One Marina, 128 of the 131 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+75 and 318 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| One Marina | 1 | G+75 | 318 | - |
Unit mix on the filing: 318 residential.
Legal and disputes
What disputes are disclosed?
1 complaint is on the MahaRERA record for One Marina, with orders passed in 1 of them.
1complaint
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000591160 | 13/07/2024 | propertycloud Realty specifier Pvt Ltd. vs Valencia and Mishal Ventures Pvt Ltd | order passed |
Legal & Litigation
The promoter has declared 7 court cases on this project to MahaRERA. 7 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Mumbai High Court | 3387 | 2018 | Pending |
| Mumbai High Court | 3388 | 2018 | Pending |
| Mumbai High Court | 3389 | 2018 | Pending |
| Mumbai High Court | 3392 | 2018 | Pending |
| Mumbai High Court | 3393 | 2018 | Pending |
| Mumbai High Court | 3394 | 2018 | Pending |
| Small Causes Court | 355 | 2018 | Pending |
Location, Land & Connectivity
Located at Chira Bazar Chandanwadi, Shamaldas Gandhi Marg, Mumbai, Mumbai Suburban, 400002. Per the filed land record, the plot is bounded to the north by 15mtr Chandanwadi Road, to the south by 29 mtr Shamaldas gandhi Marg, to the east by Rehab Building and to the west by C S No 429. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Nariman Point / Fort | 4 km |
| Lower Parel / Worli business district | 5 km |
| Bandra Kurla Complex (BKC) | 13 km |
| Chhatrapati Shivaji Int'l Airport | 15 km |
| Powai / Hiranandani business park | 19 km |
| Andheri MIDC / SEEPZ | 20 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.