Mumbai/Project record

MahaRERA · the public record

PODDAR WONDERCITY PHASE - IV

JOVELI VILLAGE · Poddar Housing and Development Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020041

Delivery and registration

When is the project declared for completion?

PODDAR WONDERCITY PHASE - IV is registered with MahaRERA as P51700020041 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020041
Registered on19 Mar 2019
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PODDAR WONDERCITY PHASE - IV record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Poddar Housing is the promoter of record on 20 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

20projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PODDAR WONDERCITY PHASE - IV in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
A11G+2031 Jul 2022
A21G+2031 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JOVELI VILLAGE, -, Mumbai City, Mumbai City, 421503. Per the filed land record, the plot is bounded to the north by JOVELI VILLAGE S NO 27, to the south by JOVELI VILLAGE S NO 29 H NO 1, to the east by JOVELI VILLAGE S NO 28 and to the west by JOVELI VILLAGE S NO 30 H NO 3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Poddar Housing And Development Limited is the promoter on 13 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Poddar Housing And Development Limited project & its RERA track record →

Other flagged projects by Poddar Housing And Development Limited

Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
FlaggedMumbai City
Poddar Housing And Development Limited
FlaggedThane
Poddar Housing And Development Limited
Past its declared completion dateThane

Other RERA-registered projects in Badlapur

Jagannath Paradise
possession by Sep 2026 · Mayur Group
JAY Meghdoot Chsl
possession by Sep 2026 · S R Developers
Kendale Emeralds
possession by Sep 2026 · Kendale Developers
Krishna Sudama Residency
possession by Sep 2026 · SAI Homes
MAA Bhawani Empire
Deregistered by MahaRERA · possession by Sep 2026 · MAA Bhawani Construction
Raghu Anand Villa
possession by Sep 2026 · United Developers

Other RERA-registered projects in Thane

Poddar Wondercity Phase - V
declared completion Jun 2024 · Poddar Housing And Development Limited
Poddar Wondercity Phase - VI
declared completion Jun 2024 · Poddar Housing And Development Limited
Pokhriyal Paradise
declared completion Oct 2022 · Pokhriyal AND Associates
Pokhriyal Paramount
possession by Dec 2028 · Pokhriyal AND Associates
Pooja Residency
declared completion Dec 2019 · Bhaskar Ratna Reddy
Pool City Lakshadweep Villa
possession by Dec 2028 · Meravilla Infra Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026