MahaRERA Property Intelligence · Mumbai City

PODDAR SPRAHA DIAMOND PHASE-I

P51900002986 · Subhash Nagar · promoter Poddar Housing And

Certificate SignedDue 30 Sep 2022

Delivery & Registration

MahaRERA registrationP51900002986
Registered on04 Aug 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Poddar Housing And is the promoter of record on 18 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
PODDAR SPRAHA DIAMOND WING A1G+1830 Jun 2021
PODDAR SPRAHA DIAMOND WING B1G+1830 Jun 2021

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000039750026/09/2023Sushant Chandrakant Gaikwad vs Poddar Housing and Development Limitedorder passed
CC1240034205/10/2024pooja sharma vs Pooja Sharma and Kishan Sharmaorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202231 Mar 2022With refernce to MahaRERA order No:- 14/2020 MahaRERA/Secy/Order/26/2020 we would like to further extend project completion till 31-Mar-2022, considering lockdown and Pandemic due

Location, Land & Connectivity

Located at Subhash Nagar, Off St. Anthony road, Mumbai City, Mumbai City, 400071. Per the filed land record, the plot is bounded to the north by MHADA BUILDING NO 46, to the south by CTS NO 1504 A PART, to the east by NALLAH and to the west by MHADA BUILDING NO 44 AND 45. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport6 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Poddar Housing And Development Limited is the promoter on 13 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Poddar Housing And Development Limited project & its RERA track record →

Other flagged projects by Poddar Housing And Development Limited

Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
FlaggedThane
Poddar Housing And Development Limited
Past its declared completion dateThane
Poddar Housing And Development Limited
Past its declared completion dateThane

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai City

Pole Star
possession by Dec 2027 · OM Shanti Housing Development Company
Prabhat
declared completion Dec 2019 · Sunil Saiya & Alpa Saiya
Prabhat
declared completion Jan 2020 · M/s Pancharatnaa
Prabhav Arisha
possession by Mar 2027 · Balaji Associates
Prabhudas Tower
possession by Jul 2028 · Sarrah Construction
Prakash Cotton Mill
declared completion Dec 2017 · Mhada

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026