PODDAR WONDERCITY PHASE - III

P51700020038 · JOVELI VILLAGE · promoter Poddar Housing And

Certificate SignedDue 30 Sep 2024

Delivery & Registration

MahaRERA registrationP51700020038
Registered on19 Mar 2019
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Poddar Housing And is the promoter of record on 18 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
B71G+2030 Sep 2023
B81G+2030 Sep 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at JOVELI VILLAGE, -, Mumbai City, Mumbai City, 421503. Per the filed land record, the plot is bounded to the north by JOVELI VILLAGE S NO 30 H NO 1 and 2, to the south by JOVELI VILLAGE S NO 29 H NO 2, to the east by SAPE VILLAGE GUT NO 4 OF 1 and to the west by JOVELI VILLAGE S NO 30 H NO 3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Poddar Housing And Development Limited is the promoter on 13 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Poddar Housing And Development Limited project & its RERA track record →

Other flagged projects by Poddar Housing And Development Limited

Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
Not filing quarterly progress reportsThane
Poddar Housing And Development Limited
FlaggedMumbai City
Poddar Housing And Development Limited
FlaggedThane
Poddar Housing And Development Limited
Past its declared completion dateThane

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Poddar Wondercity Phase - IV
declared completion Jul 2023 · Poddar Housing And Development Limited
Poddar Wondercity Phase - V
declared completion Jun 2024 · Poddar Housing And Development Limited
Poddar Wondercity Phase - VI
declared completion Jun 2024 · Poddar Housing And Development Limited
Pokhriyal Paradise
declared completion Oct 2022 · Pokhriyal AND Associates
Pokhriyal Paramount
possession by Dec 2028 · Pokhriyal AND Associates
Pooja Angan
declared completion Dec 2022 · Sairaj Projects

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026