Mumbai/Project record

MahaRERA · the public record

Premleela Heights

VILLAGE PAHADI · Prem Leela Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012764

Delivery and registration

When is the project declared for completion?

Premleela Heights is registered with MahaRERA as P51800012764 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012764
Registered on07 Sep 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Premleela Heights record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Prem Leela Developers is the promoter of record on 40 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

40projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Premleela Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
Premleela Heights1G+1831 Dec 2022

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for Premleela Heights, with orders passed in 7 of them.

10complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001267830/12/2017DHARAMSHI S PATEL vs M/s PREMLEELA DEVELOPERSorder passed
CC00600000019778730/07/2021SACHIN VITTHAL SAWANT vs Premleela developersorder passed
CC00600000037489822/03/2023Madhav Arjun Suryawanshi vs M/s. Prem Leela Developersorder passed
CC00600000037528916/04/2023Madhav Arjun Suryawanshi vs Prem Leela Developerspending / no order on file
CC00600000037540526/04/2023Madhav Arjun Suryawanshi vs Prem Leela Developerspending / no order on file
CC00600000037541027/04/2023Madhav Arjun Suryawanshi vs Prem Leela Developerspending / no order on file
CC00600000040865430/05/2024Preeti Amit Pednekar vs Shri Shailesh Prem Shankar Ravalorder passed
CC00600000043975121/03/2024ANIL SADHURAM BHURE vs M/S PREM LEELA DEVELOPERSorder passed
CC00600000044975421/03/2024SAI SWANAND PANDIT vs M/S PREM LEELA DEVELOPERSorder passed
CC1250071028/02/2025RAKESH BADALBHAI SOLANKI vs Prem Leela Developersorder passed

Location, Land & Connectivity

Located at VILLAGE PAHADI, SHREYAS COLONY ROAD NO 1 GOREGAON EAST MUMBAI, Borivali, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by 447, to the south by Existing Road and 454A, to the east by Existing Road and to the west by 455A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

Premsagar
declared completion Dec 2025 · Ankur Premises Developers LLP
Prerana Chsl
declared completion Jul 2026 · Pratham Varadvinayak Infra Developers LL
Presidence One
possession by Jan 2030 · N Khan Construction Works LLP
Prestige Daffodils Chsl
possession by Dec 2026 · Prestige Estates Projects Limited
Prestige Residency
possession by Jun 2028 · Homeland Realtors & Developers Priva
Prestige Trade Centre- Offices
possession by Dec 2027 · Prestige Mulund Realty Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026