PURAV HEIGHTS

Girgoan · BHRUGU CHANDRAKANT KHAKHAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900005752

Delivery and registration

When is the project declared for completion?

PURAV HEIGHTS is registered with MahaRERA as P51900005752 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900005752
Registered on11 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PURAV HEIGHTS record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Bhrugu Chandrakant Khakhar is the promoter of record on 121 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

121projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PURAV HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
PURAV HEIGHTS WING A1G+21-
PURAV HEIGHTS WING B1G+21-
PURAV HEIGHTS WING C1G+20-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Girgoan, Tatya Ghapure Path, Ward ABCD, Mumbai City, 400004. Per the filed land record, the plot is bounded to the north by TATYA GHARPURE PATH, to the south by CS NO 291 CS NO 290, to the east by BHASKAR BUWA BAKHALE PATH and to the west by CS NO 286. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort3 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport16 km
Powai / Hiranandani business park20 km
Andheri MIDC / SEEPZ20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Girgaum

Aaditya Residences
possession by Dec 2026 · M/s. A.k. Developers
Shreepati Bayview
Deregistered by MahaRERA · possession by Dec 2026 · Shreepati Build Infra Investment Limited
NEO Amity
possession by Dec 2026 · Naresh Kesarimal Mehta
Onyx
possession by Dec 2026 · Naminath Erector And Developers LLP
Promesa Castor
possession by Dec 2026 · Darshan Group
Raajdeep Arcade
possession by Dec 2026 · Raajdeep Builders AND Developers

Other RERA-registered projects in Mumbai City

Q Gardens Realty
declared completion Jul 2019 · Q Gardens Realty
Qamar E Bani Hashim
possession by Dec 2028 · Commercial Developers
Qamar Terrace
possession by Dec 2030 · Not Available
Queens Corner
possession by Dec 2028 · Prathmeshwara Lifespaces LLP
RA Residences
possession by Dec 2027 · R A Associates
Raajdeep Arcade
possession by Dec 2026 · Raajdeep Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.