30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007692

Delivery and registration

When is the project declared for completion?

PUSHPAK HEIGHTS is registered with MahaRERA as P51800007692 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007692
Registered on17 Aug 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PUSHPAK HEIGHTS record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Pushpak Realties is the promoter of record on 131 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

131projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PUSHPAK HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
PUSHPAK HEIGHTS1G+23-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for PUSHPAK HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005789211/09/2019PULIN NAVINCHANDRA KUSUMGAR vs Jignesh Shahorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Project was nearing completion but due to discrepancy in calculations of land rate as raised by revenue and planning authorities, work had came to standstill. As the Plot is reflec
30 Dec 202030 Jun 2022Due to “SECOND WAVE” which crested in the state of Maharashtra forcing the state government to once again impose fresh restrictions and labour exodus in the country to their native

Location, Land & Connectivity

Located at malad, daftary road, Andheri, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by ROAD, to the south by SOUTH VILLAGE BOUNDARY, to the east by ROAD and to the west by CTS NO 534 535 536 537. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shreeji Plaza Wing B
possession by Sep 2026 · Siddharth Enterprises
Linkpark
possession by Oct 2026 · Adarsh Industrial Estate Private Limited
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
possession by Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
possession by Dec 2026 · Jinam Realtors

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Pushpanjali Residency
declared completion Dec 2025 · Shree Dham Developers
Qadri Manzil
possession by Dec 2029 · Qadri Constructions
Quality Victoria
declared completion Dec 2023 · Quality Construction Developers
Queen Of Spaces
possession by Jun 2027 · Space India Builders And Developers LLP
Queens Glory
possession by Dec 2027 · Vaibhavlaxmi Builders & Developers
Queens Park
declared completion Dec 2025 · V Laxmi Estate Developers Private Limite

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026