Mumbai/Project record

MahaRERA · the public record

Reality Heights

Jawhar · Reality Builders and Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000050325

Delivery and registration

When is the project declared for completion?

Reality Heights is registered with MahaRERA as P99000050325 and the promoter has declared completion for 30 Dec 2027.

30 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000050325
Registered on05 Apr 2023
Promoter-declared completion30 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Reality Heights record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Reality Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Reality Heights1G+431 Dec 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Jawhar, Jawhar , Jawhar, Palghar, 401603. Per the filed land record, the plot is bounded to the north by CTS No 1112, to the south by Colony Road, to the east by Adjoin Road and to the west by CTS No 1110. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jawhar

Durvankur Heights
possession by May 2028 · Himanshu Sham Tendulkar
THE Empire
declared completion Mar 2026 · Shahji Infra
Gulmohar Avenue
declared completion Apr 2025 · Himanshu Sham Tendulkar
Noor Residency
Past its declared completion date · declared completion Dec 2024 · New Creative Construction
Sara Govind Apartment
declared completion Dec 2023 · Sara Developers AND CO
Rijvita Serenity
Past its declared completion date · declared completion Dec 2018 · Rijvita Developers Pvt. LTD

Other RERA-registered projects in Palghar

Rebecca Paul Apartments
declared completion Dec 2024 · Rebecca Goa Realtors
Redevelopement Of Sagar Prakash Hsg Co-Op Soc
possession by Dec 2027 · Trimurti Construction
Redevelopment Of Ajanta Co-Op Hou.soc Ltd
possession by Dec 2028 · S R Builders & Developers
Redevelopment Of Chinmay Co-Operative Housing Society Ltd
possession by Jan 2027 · Neom Construction
Redevelopment Of Datta Krupa CHS Ltd
possession by Jul 2027 · Ramkala Infrastructure
Redevelopment Of Rambha Co-Operative Housing Ltd
possession by Jan 2027 · Shree Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026