Mumbai/Project record

MahaRERA · the public record

RIJVITA SERENITY

Mumbai Suburban · RIJVITA DEVELOPERS PVT. LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

12 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

12 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000011810

Delivery and registration

When is the project declared for completion?

RIJVITA SERENITY is registered with MahaRERA as P99000011810 and the promoter has declared completion for 12 Dec 2018.

12 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000011810
Registered on31 Aug 2017
Promoter-declared completion12 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RIJVITA SERENITY record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RIJVITA SERENITY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
RIJVITA SERENITY1G+5-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for RIJVITA SERENITY, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000053622/11/2017harish sharma vs ajit damji dedhiaorder passed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401603. Per the filed land record, the plot is bounded to the north by LAYOUT ROAD, to the south by PLOT NO 3, to the east by PLOT NO 9 and to the west by STATE HIGHWAY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~178 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park178 km
Bandra Kurla Complex (BKC)181 km
Andheri MIDC / SEEPZ182 km
Chhatrapati Shivaji Int'l Airport182 km
Lower Parel / Worli business district185 km
Nariman Point / Fort185 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jawhar

Reality Heights
possession by Dec 2027 · Reality Builders And Developers
Durvankur Heights
possession by May 2028 · Himanshu Sham Tendulkar
THE Empire
declared completion Mar 2026 · Shahji Infra
Gulmohar Avenue
declared completion Apr 2025 · Himanshu Sham Tendulkar
Noor Residency
Past its declared completion date · declared completion Dec 2024 · New Creative Construction
Sara Govind Apartment
declared completion Dec 2023 · Sara Developers AND CO

Other RERA-registered projects in Palghar

Rishabh Heights
declared completion Dec 2023 · Nandish City Infratech & Developers
Rising Height
declared completion Dec 2024 · M/S Rising Enterprises
Rite 24
possession by Dec 2028 · Rite 24 Developers
Ritika Heights
possession by Dec 2026 · Akajit Developers LLP
Ritu Gardenia Phase 2
possession by Dec 2027 · Ritu Builders AND Developers
Riyansh Enclave
possession by Dec 2027 · Vardaan Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026