31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000029208

Delivery and registration

When is the project declared for completion?

Sara Govind Apartment is registered with MahaRERA as P99000029208 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000029208
Registered on10 May 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sara Govind Apartment record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sara Developers is the promoter of record on 179 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

179projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sara Govind Apartment in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Sara Govind Apartment1G+531 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JAWHAR, MAIN ROAD, Jawhar, Palghar, 401603. Per the filed land record, the plot is bounded to the north by 9 METER ROAD, to the south by CTS NO 872, to the east by CTS NO 876-877-879 and to the west by ROAD AND THEREAFTER VITTHAL TEMPLE. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sara Developers AND CO is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Jawhar

Reality Heights
possession by Dec 2027 · Reality Builders And Developers
Durvankur Heights
possession by May 2028 · Himanshu Sham Tendulkar
THE Empire
declared completion Mar 2026 · Shahji Infra
Gulmohar Avenue
declared completion Apr 2025 · Himanshu Sham Tendulkar
Noor Residency
Past its declared completion date · declared completion Dec 2024 · New Creative Construction
Rijvita Serenity
Past its declared completion date · declared completion Dec 2018 · Rijvita Developers Pvt. LTD

Other RERA-registered projects in Palghar

Saravali Classic
possession by Dec 2028 · Maverick Builders AND Developers
Sargam Avenue
declared completion Mar 2018 · Shantee Housing
Sarita Appartment
declared completion Sep 2020 · Kshipra Developers
Saroja Residency
declared completion Dec 2024 · D S Enterprise
Sathya Lifestyles Building NO 12
declared completion Nov 2025 · Santosh Arjun Naik
Sathya Lifestyles Phase 2
declared completion Mar 2024 · Sathya Lifestyles PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026