Mumbai/Project record

MahaRERA · the public record

ROSELLA

Mumbai City · Vijaya Residency

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900005842

Delivery and registration

When is the project declared for completion?

ROSELLA is registered with MahaRERA as P51900005842 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900005842
Registered on14 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ROSELLA record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vijaya Residency is the promoter of record on 149 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

149projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ROSELLA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
Rosella1G+21-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ROSELLA, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019352622/07/2020HEMAL RASIKLAL PAREKH vs VIJAYA RESIDENCY PVT LTDorder passed

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400075. Per the filed land record, the plot is bounded to the north by BLDG 150, to the south by BLDG 146, to the east by BLDG 147 and to the west by 40 FEET ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park4 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Mohite Marvel
possession by Sep 2026 · Mohite Realtors LLP
OM Priyadarshani
possession by Sep 2026 · Aakruti Enterprises
Prime Vista
possession by Sep 2026 · Rupvakula Properties Pvt. LTD
Damji Shamji Corporate Square - Wing C
possession by Dec 2026 · Coronate Constructions
Ashirwad CHS LTD
possession by Dec 2026 · Shreedham Developers
Drushti Emerald
possession by Dec 2026 · Samarth Drushti Developers

Other RERA-registered projects in Mumbai City

Royal Heights
possession by Dec 2026 · S.a. Enterprises
Royal Meadows AND Royal Nest AND Royal Crest
declared completion May 2018 · Dhankrishna Estates PVT LTD
Royal OAK
possession by Nov 2027 · Greenbuilding Lifescapes LLP
Royal Residency C Phase I
declared completion Aug 2025 · Devang Hemantkumar Vyas
Royale Imperia
declared completion Dec 2025 · Mitha Developers
Runwal Malabar
possession by Jun 2032 · Runwal Developers Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026