ROSHNI

Mumbai Suburban · ASPY PHIROZE CAPTAIN

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006599

Delivery and registration

When is the project declared for completion?

ROSHNI is registered with MahaRERA as P51800006599 and the promoter has declared completion for 30 Oct 2018.

30 Oct 2018

declared completion

95months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006599
Registered on14 Aug 2017
Promoter-declared completion30 Oct 2018
Current statusCertificate Signed
Against todayabout 95 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ROSHNI record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ROSHNI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
ROSHNI1G+11-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for ROSHNI, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005624220/09/2018Urmila Sanjay Didwania vs Aspy Captainorder passed
CC00600000005754404/01/2019Urmila Sanjay Didwania vs Aspy Captainorder passed
CC00600000043972919/03/2024Guniben Pravin Shah vs Aspy Captainorder passed

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400057. Per the filed land record, the plot is bounded to the north by BY 213 215, to the south by DIXIT ROAD, to the east by 15 FEET PRIVATE RAOD and to the west by BY PLOT NO 213 214 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Andheri MIDC / SEEPZ4 km
Bandra Kurla Complex (BKC)4 km
Powai / Hiranandani business park6 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle East

Moti Madhav
possession by Sep 2026 · Aadhya Skyvista
Neumec Niwara
possession by Sep 2026 · Neumec Venture
Yeshwant Sadan
possession by Sep 2026 · ARG Life Spaces LLP
Vile Parle Mamata Chsl
possession by Oct 2026 · Dhruv Infrastructure
Vanmala Nivas CHS LTD
possession by Nov 2026 · AMI Infra Realtors
ZEE Nayak
possession by Dec 2026 · Pragatee ZEE

Other RERA-registered projects in Mumbai Suburban

Roswalt Shatataraka Chsl
possession by Sep 2028 · Roswalt Realty Private Limited
Roswalt Zaiden
possession by Dec 2028 · A S Hightech LLP
Royal Accord
declared completion Dec 2025 · Viva Homes Private Limited
Royal Altezza
declared completion Aug 2026 · Shri Ganesh Developers
Royal Bliss
possession by Dec 2027 · Royal Developers
Royal Crystal Wing B
declared completion Dec 2021 · Royal Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026