MahaRERA Property Intelligence · Mumbai Suburban

Ruparel Pride

P51800020602 · Kurla · promoter Shree Siddhivinayak Classic

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51800020602
Registered on26 Apr 2019
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Ruparel Pride1G+23-

Complaints & Orders

10 complaints are on the MahaRERA record for this project, with orders passed in 7. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000008987309/07/2019RAMKRISHNA SHRIDHAR PHANSEKAR vs MS RE BUILTorder passed
CC00600000017153513/11/2019Mayur C Shikhare vs Shree Siddhivinyak Classic Construction Pvt. Ltd.order passed
CC00600000039590423/05/2023jamuna s charania vs Ruparel realityorder passed
CC00600000025154522/06/2022NEHRU NAGAR SHANTI BHUVAN CHSL SOCIETY (society) vs AMIT MAHENDRA RUPARELorder passed
CC00600000026193615/07/2022Dr Jayaben S Charania vs Ruparel Realtyorder passed
CC00600000029247726/08/2022Dr Jayaben S Charania vs Ruparel realtyorder passed
CC00600000030310919/10/2022Dr Jayaben S Charania vs Santokben Charania, Jamuna Charaniaorder passed
CC1260288416/05/2026Swapnil Subhash Bhalerao vs Shree Siddhivinayak Classic Construction Private Limitedpending / no order on file
CC1260346905/06/2026HANSA AMIT MAKWANA vs Shree Siddhivinayak Classic Construction Private Limitedpending / no order on file
CC1260442716/07/2026Shahana Bano Idrisi vs Shree Siddhivinayak Classic Construction Private Limitedpending / no order on file

A co-operative housing society is the complainant here (NEHRU NAGAR SHANTI BHUVAN CHSL SOCIETY) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202431 Dec 2025M/s. Shree Siddhivinayak Classic Construction Pvt. Ltd., the promoter of Ruparel Pride (RERA Registration No. P51800020602), respectfully submits a request for an extension of the

Location, Land & Connectivity

Located at Kurla, Nehru Nagar, Mumbai, Mumbai Suburban, 400024. Per the filed land record, the plot is bounded to the north by Adjoining Nalla, to the south by Existing Road, to the east by Adjoining Bldg No 89 and to the west by Mother Dairy Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Siddhivinayak Classic Construction Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shree Siddhivinayak Classic Construction Priv

Shree Siddhivinayak Classic Construction Private Limited
FlaggedMumbai Suburban
Shree Siddhivinayak Classic Construction Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Nehru Nagar

OM Nandadeep CO-OP. Hsg. Soc. LTD
possession by Oct 2026 · OM Nandadeep CO-OP Housing Society Limit
Ratnadeep Heights
possession by Oct 2026 · KRV Realty
Raghav Parijat
possession by Dec 2026 · Raghav Realty Developers
Hareshwar Pride
possession by Dec 2026 · Satyadeep Realtors Pvt. Ltd.
Nehru Nagar Vishwadham CHS LTD
possession by Dec 2026 · Apcon Construction Company
Nehru Nagar Nirmal C.h.s. Ltd
possession by Dec 2026 · Deraiya Realtors Private Limited

Major developers building in Nehru Nagar

Other RERA-registered projects in Mumbai Suburban

Ruparel Primero
declared completion Dec 2025 · Shree Siddhivinayak Classic Construction
Ruparel Pristine
possession by Dec 2026 · Shiddhivinayak Developers
Ruparel Skygreens I
possession by Dec 2026 · Shree Siddhivinayak Infrastructure &
Ruparel Stardom
possession by Jun 2028 · AMI Modispaces LLP
Ruparel Urbana
possession by Dec 2028 · R R Builders
Ruparel Westsky
possession by Dec 2027 · Ruparel Shreeji Construction PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026