Ruparel Primero

Chembur · Shree Siddhivinayak Classic Construction Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800021096

Delivery and registration

When is the project declared for completion?

Ruparel Primero is registered with MahaRERA as P51800021096 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800021096
Registered on31 May 2019
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ruparel Primero record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ruparel Primero in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
Ruaprel Primero1G+19-

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for Ruparel Primero, with orders passed in 5 of them.

6complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019417625/04/2021Dr. Erbaz Momin vs Amit Ruparelorder passed
CC00600000023115513/05/2022Rohini Pralhad Musale vs M/s. Millennium Developersorder passed
CC00600000028213302/08/2022Shyamji R Gupta vs M/s. Millennium Developersorder passed
CC00600000029260217/09/2022Varsha Limkar vs M/s. Millennium Developersorder passed
CC00600000030311501/11/2022Laxman Sabnis vs M/s. Millennium Developersorder passed
CC1250110002/04/2025Kamrul Khan vs Shree Siddhivinayak Classic Construction Private Limitedpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025We, M/s. Shree Siddhivinayak Classic Construction Pvt. Ltd., the promoter of Ruparel Primero (RERA Reg. No. P51800021096), kindly request an extension of the project completion dat

Location, Land & Connectivity

Located at Chembur, Tilak Nagar, Mumbai, Mumbai Suburban, 400089. Per the filed land record, the plot is bounded to the north by Plot NO 121, to the south by Plot No 118, to the east by 9 mtr wide Road and to the west by R G Open Plot. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Siddhivinayak Classic Construction Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shree Siddhivinayak Classic Construction Priv

Shree Siddhivinayak Classic Construction Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Chembur

Orient Regency Building No. 1
possession by Dec 2026 · Orient Combine
Sree Sudarshan Heights
possession by Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
possession by Dec 2026 · Chinnaiah Venkatesh Gowda
Promesa Midtown
possession by Dec 2026 · Darshan Properties
Vishwasangam
possession by Dec 2026 · Vishwashakti Cooperative Housing Society
Ampple-ONE
possession by Mar 2027 · Amppletech Projects Private Limited

Other RERA-registered projects in Mumbai Suburban

Ruparel Pristine
possession by Dec 2026 · Shiddhivinayak Developers
Ruparel Skygreens I
possession by Dec 2026 · Shree Siddhivinayak Infrastructure &
Ruparel Stardom
possession by Jun 2028 · AMI Modispaces LLP
Ruparel Urbana
possession by Dec 2028 · R R Builders
Ruparel Westsky
possession by Dec 2027 · Ruparel Shreeji Construction PVT LTD
Ruparel Zinnia
possession by Jun 2028 · AMI Modispaces LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026