SAI DARSHAN

Thane · DINESH GEHARILAL JAIN

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700010543

Delivery and registration

When is the project declared for completion?

SAI DARSHAN is registered with MahaRERA as P51700010543 and the promoter has declared completion for 31 Jan 2021.

31 Jan 2021

declared completion

68months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700010543
Registered on31 Aug 2017
Promoter-declared completion31 Jan 2021
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI DARSHAN record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI DARSHAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SAI DARSHAN1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Kalyan, Thane, 421302. Per the filed land record, the plot is bounded to the north by PLOT SURVEY NO 138, to the south by KALYAN BHIWANDI ROAD, to the east by PLOT SURVEY NO 138 and to the west by PLOT SURVEY NO 135 P. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park20 km
Andheri MIDC / SEEPZ22 km
Chhatrapati Shivaji Int'l Airport25 km
Bandra Kurla Complex (BKC)27 km
Lower Parel / Worli business district35 km
Nariman Point / Fort43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Anantam Heights
possession by Oct 2026 · Kanak Realty
Upper Thane - Woodlands A, B AND J
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

SAI Darshan
possession by Apr 2027 · Trimurti Enterprises
SAI Darshan
possession by Nov 2026 · SAI Krupa Builders
SAI Darshan D Wing
possession by Dec 2029 · Trimurti Enterprises
SAI Darshan Godavari
possession by Sep 2028 · Sai Laxmi Developers
SAI Datta Kripa
possession by Dec 2027 · Bhalchandra Vinayak Wadnerkar
SAI Deep Residency
declared completion Dec 2025 · Kishor Ratan Chaudhary

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.