SAMPADA HEIGHTS

Parel · SAMPADA REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900004994

Delivery and registration

When is the project declared for completion?

SAMPADA HEIGHTS is registered with MahaRERA as P51900004994 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900004994
Registered on09 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMPADA HEIGHTS record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sampada Realtors is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAMPADA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
SAMPADA HEIGHTS1G+22-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for SAMPADA HEIGHTS, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019542529/12/2020Shradha Arunkumar Ambawat vs Sampada Realtorsorder passed
CC00600000019542629/12/2020Alisha Ajit Ambawat vs Sampada Realtorsorder passed
CC00600000019256411/02/2020ARUNKUMAR AMBAWAT vs ASHOK MAHAAVIRPRASAD MURARKAorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020SUDDEN DEMISE OF ONE OF THE WORKING PARTNER.

Location, Land & Connectivity

Located at Parel, Mumbai City, Mumbai City, 400012. Per the filed land record, the plot is bounded to the north by 689 AND 690, to the south by 687, to the east by G D AMBEKAR MARG and to the west by 686. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)123 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parel

Inspire
possession by Sep 2026 · R K Constructions
K RAS Residency
possession by Sep 2026 · K RAS Group
Kinjal Pride
possession by Oct 2026 · Hi Rock Construction Pvt Ltd
Bhivawani Chawl
possession by Dec 2026 · MS Radhakrishna Developer
Bhoiwada Chandra Bhuvan CHS Ltd
possession by Dec 2026 · Avadhoot Techno Consultant And Engineers
Ruparel Jewel
possession by Dec 2026 · Renuka Realtors

Major developers building in Parel

Other RERA-registered projects in Mumbai City

Samruddhi CHS LTD
declared completion Dec 2021 · Unispace Developers Private Limited
San Petros Residency
possession by Jun 2027 · SAN Petros Properties
Sanghvi Estella
possession by Dec 2026 · Shree Naminath Lifespace LLP
Sanghvi Evana
declared completion Dec 2021 · Sanghvi Premises Private Limited
Sanghvi Heights Phase 2
declared completion Jun 2025 · Sanghvi Premises Private Limited
Sanghvi Morya
possession by Dec 2030 · Firsdale Enterprises Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026