MahaRERA Property Intelligence · Mumbai City

SAMRUDDHI CHS LTD

P51900005827 · promoter Unispace Developers Private

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP51900005827
Registered on14 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Unispace Developers Private is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
SAMRUDDHI CHS LTD1G+24-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202131 Dec 2020The Promoter had complied with all the conditions of the I.O.D. and the building or the project viz. Samruddhi CHS Ltd. which was practically completed in the year 2014 and it is f

Location, Land & Connectivity

Located at Ward FNorth, Mumbai City, 400014. Per the filed land record, the plot is bounded to the north by 8 MT WIDE HINDU COLONY ROAD NO 5, to the south by EXISTING BUILDING, to the east by EXISTING BUILDING and to the west by 18 MT WIDE L N ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)6 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar East

Anchor Sky D
Deregistered by MahaRERA · possession by Dec 2026 · Om Shanti Housing Development Company
Yash Supriya
possession by Dec 2026 · Yash Construction Company
Bhalchandra Niwas CHS
possession by Dec 2026 · Ishaan Realtors
Nine Reflex
possession by Dec 2026 · Reflex Projects LLP
Chirag Heights
possession by Dec 2026 · Nettheim Builders LLP
EL Mejor
possession by Dec 2026 · Arth Realtech Spaces PVT LTD

Other RERA-registered projects in Mumbai City

Samruddhi Heights
declared completion Mar 2021 · High Rise Realty Private Limited
Samta Parel
declared completion Jan 2023 · Newlook Constructions Pvt. Ltd
San Petros Residency
possession by Jun 2027 · SAN Petros Properties
Sangeet Jyoti
declared completion Jun 2025 · Prime Housing
Sanghvi Estella
possession by Dec 2026 · Shree Naminath Lifespace LLP
Sanghvi Evana
declared completion Dec 2021 · Sanghvi Premises Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026