MahaRERA Property Intelligence · Mumbai Suburban

sanghvi ATLANTA

P51800006480 · promoter Atlanta Properties

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP51800006480
Registered on14 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Atlanta Properties is the promoter of record on 9 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
sanghvi ATLANTA1G+2330 Jun 2023

Complaints & Orders

32 complaints are on the MahaRERA record for this project, with orders passed in 32. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000029271026/09/2022MAHESH MAHADEV TAWADE vs Atlanta Propertiesorder passed
CC00600000033395213/04/2024Domnic Rosario James vs Pramod Salviorder passed
CC00600000039689316/01/2024SAGINA ZAKIR SAYYAD vs M/S Atlanta Propertiesorder passed
CC00600000039754621/09/2023Arati Santosh Ghadigaonkar vs Atlanta Propertiesorder passed
CC00600000039772808/12/2023Mahesh Madhukar Kadam vs Atlanta Propertiesorder passed
CC00600000039772908/12/2023Nilesh Suryakant Kavade vs Atlanta Propertiesorder passed
CC00600000039773008/12/2023Prashant D Shelar vs Atlanta Propertiesorder passed
CC00600000039773108/12/2023Ashokkumar Prajapati vs Atlanta Propertiesorder passed
CC00600000039773208/12/2023Shivsharan Rammanohar Gupta vs Atlanta Propertiesorder passed
CC00600000040847504/01/2024Sameedha Sachin Nawage vs M/S Atlanta Propertiesorder passed
CC00600000042886220/03/2024Sujata Sadashiv Bachal vs M/s. Atlanta Propertiesorder passed
CC00600000042918310/02/2024Ajay Sitaram Birwatkar vs Atlanta Propertiesorder passed
CC00600000042918710/02/2024Vinayak Rane vs Atlanta Propertiesorder passed
CC00600000042918812/02/2024Prashant Yashwant Bandal vs Atlanta Propertiesorder passed
CC00600000042918910/02/2024Dibya Kanti Maiti vs Atlanta Propertiesorder passed
CC00600000042919210/02/2024Sanjay Solanki vs Atlanta Propertiesorder passed
CC00600000042922913/02/2024Anup Kumar Pal vs Atlanta Propertiesorder passed
CC00600000042923217/02/2024Kamlesh Desai vs Atlanta Propertiesorder passed
CC00600000042923917/02/2024Sameer Anant Juwatkar vs Atlanta Propertiesorder passed
CC00600000042929320/02/2024Senthil Kumar Mayilvahanam vs Atlanta Propertiesorder passed
CC00600000042959830/05/2024Madhaba Nayak vs Atlanta Propertiesorder passed
CC00600000042960111/03/2024Mahendra Laxman Rane vs Atlanta Propertiesorder passed
CC00600000042960421/03/2024Yogesh Devadiga vs Atlanta Propertiesorder passed
CC00600000047977403/04/2024MAHESH JAIRAM GHAG vs Pratik Salviorder passed
CC00600000047998007/04/2024Rahul Devendra Singh vs M/S. Atlanta Propertiesorder passed
CC00600000047998610/04/2024Vipul Gautam Satpute vs Pratik Salviorder passed
CC00600000048007815/04/2024Sudhir Balkrishna Gholap vs Pramod Salviorder passed
CC00600000048008215/04/2024sarika amogh yadav vs MR PRATIK SALVIorder passed
CC00600000048010323/04/2024SAHADEV SHANTARAM PARAB vs ATLANTA PROPERTIESorder passed
CC00600000048028530/04/2024Rashmi Prabhakar Rasam vs Atlanta Propertiesorder passed
CC00600000058093226/06/2024Aarti Shailesh Satle vs Atlanta Propertiesorder passed
CC1240127029/12/2024Komal Ramchandra Yadav vs atlanta propertiesorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2024We are facing the worst labour and financial issue in this time because of that we are to go ahead with construction of the building. Due to scarcity of demand in housing industry,
30 Dec 202230 Jun 2023Due to unavoidable circumstances where whole world is fighting not just for Covid – 19 pandemic but also difficult to survive financially. We are facing the worst labour and financ

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by Upkar Singh Chawl, to the south by Road, to the east by Amrut Shrishti Complex and to the west by Chotelal Chawl. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park4 km
Andheri MIDC / SEEPZ7 km
Chhatrapati Shivaji Int'l Airport9 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Shraddha Evoque
possession by Aug 2026 · Shraddha Landmark Private Limited
Primo
possession by Sep 2026 · Ceear Land Developers LLP
Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Sanghvi Boulevard 97 Prism
possession by Dec 2030 · Sanghvip Builders LLP
Sanghvi Crystal
possession by Feb 2028 · Sanghvip Builders LLP
Sanghvi Edge
possession by Dec 2026 · Sangvi Lifespace Private Limited
Sanghvi Horizon
possession by Dec 2028 · Sanghvi Green LLP
Sanghvi Infenia
possession by Dec 2026 · Sanghvi Spaces LLP
Sanghvi Jewel
possession by Dec 2026 · Sanghvi Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026