MahaRERA Property Intelligence · Mumbai Suburban
P51800010958 · Borivali · promoter Sanghvi Realtors
| MahaRERA registration | P51800010958 |
| Registered on | 31 Aug 2017 |
| Promoter-declared completion | 31 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 5 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Sanghvi Realtors is the promoter of record on 48 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
MahaRERA's cost filing puts construction at ~82.9% of the estimated project cost incurred as of the last certificate (₹6.28 Cr spent against a ₹7.57 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 37 homes filed with MahaRERA, 20 are sold/booked and 17 remain available (~54% sold) — selling steadily. Buyers have committed ₹14.57 Cr in agreement value so far. Of that, ₹12.02 Cr (~82%) is already collected, ₹2.55 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 20 registered agreements, the effective carpet rate is ₹20,349/sqft (typical range ₹14,516–₹25,211) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 7 | A-702 | 407 sqft (37.79 sqm) | ₹74.07 Lakh |
| Floor 7 | A-703 | 259 sqft (24.06 sqm) | ₹47.16 Lakh |
| Floor 7 | A-704 | 262 sqft (24.33 sqm) | ₹47.69 Lakh |
| Floor 7 | A-705 | 264 sqft (24.5 sqm) | ₹48.02 Lakh |
| Floor 7 | A-706 | 594 sqft (55.23 sqm) | ₹1.08 Cr |
| Floor 7 | A-709 | 388 sqft (36.09 sqm) | ₹70.74 Lakh |
| Floor 7 | A-710 | 333 sqft (30.98 sqm) | ₹60.73 Lakh |
| Floor 7 | A-711 | 366 sqft (33.96 sqm) | ₹66.57 Lakh |
| Floor 7 | A-713 | 557 sqft (51.77 sqm) | ₹1.01 Cr |
| Floor 8 | A-803 | 259 sqft (24.06 sqm) | ₹47.16 Lakh |
| Floor 8 | A-805 | 264 sqft (24.5 sqm) | ₹48.02 Lakh |
| Floor 8 | A-806 | 404 sqft (37.54 sqm) | ₹73.58 Lakh |
| Floor 8 | A-807 | 270 sqft (25.1 sqm) | ₹49.20 Lakh |
| Floor 8 | A-809 | 511 sqft (47.49 sqm) | ₹93.09 Lakh |
| Floor 9 | A-902 | 407 sqft (37.79 sqm) | ₹67.34 Lakh |
| Floor 9 | A-905 | 264 sqft (24.5 sqm) | ₹48.02 Lakh |
| Floor 9 | A-906 | 404 sqft (37.54 sqm) | ₹66.89 Lakh |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 37 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| SANGHVI JEWEL BUILDING NO 1 | 1 | G+10 | 29 | - |
| SANGHVI JEWEL BUILDING NO 2 | 1 | G+1 | 8 | - |
Unit mix on the filing: 37 non-residential (shops/offices).
1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12400070 | 10/09/2024 | AMBESH RAMNARAYAN RAJPOOT vs SANGHVI REALTORS | order passed |
The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Sep 2024 | 31 Mar 2024 | The Developer has got additional FSI due to road width provision as per Development Control Regulations and accordingly the developer has got additional FSI for constructing 8th 9t |
| 30 Sep 2024 | 31 Dec 2019 | we are proposing amendment in plan due to modification in Mumbai Development Rules (DCPR 2034), hence for the purpose of obtaining approval and to commence work we require further |
| 31 Dec 2018 | 30 Sep 2025 | The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted t |
| 31 Dec 2018 | 31 Dec 2026 | a. Outbreak of Covid – 19 : The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 w |
Located at Borivali, Kisan Road & Underia Road, Mumbai City, Mumbai City, 400064. Per the filed land record, the plot is bounded to the north by CTS 571A, to the south by UNDERIA ROAD, to the east by CTS NO 573 and to the west by KISAN ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 7 km |
| Powai / Hiranandani business park | 10 km |
| Chhatrapati Shivaji Int'l Airport | 11 km |
| Bandra Kurla Complex (BKC) | 13 km |
| Lower Parel / Worli business district | 21 km |
| Nariman Point / Fort | 29 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in SANGHVI JEWEL?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026