SANGHVI PARSSSVA CLASSIC

BHIWANDI · SHRI PARRSSSVA ARHAM CONSTRUCTIONS ENTERPRISES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700015085

Delivery and registration

When is the project declared for completion?

SANGHVI PARSSSVA CLASSIC is registered with MahaRERA as P51700015085 and the promoter has declared completion for 31 Mar 2023.

31 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700015085
Registered on23 Jan 2018
Promoter-declared completion31 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SANGHVI PARSSSVA CLASSIC record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shri Parrsssva Arham is the promoter of record on 2 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SANGHVI PARSSSVA CLASSIC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SHRI PARRSSSVA CLASSIC1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2021We are facing delay in obtaining Metro NOC for our project. Therefore request for extension of time for completion of project.
31 Mar 202131 Mar 2023Dear Sir, The extension is required for completion of building and for getting the Occupation Certificate from the authority. Therefore requesting further extension till 31/03/203.

Location, Land & Connectivity

Located at BHIWANDI, AGASKAR LANE, Mumbai City, Mumbai City, 421302. Per the filed land record, the plot is bounded to the north by ROAD, to the south by S NO 118 1 P T, to the east by ADJ H NO 3 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~25 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park25 km
Andheri MIDC / SEEPZ27 km
Chhatrapati Shivaji Int'l Airport31 km
Bandra Kurla Complex (BKC)32 km
Lower Parel / Worli business district41 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhiwandi

Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Anantam Heights
possession by Oct 2026 · Kanak Realty
Upper Thane - Woodlands A, B AND J
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Sanghvis Shri Parrsssva City 15-16
declared completion Jun 2026 · Sanghvi Premises Private Limited
Sangles Trinity
possession by Jul 2028 · Sangle Enterprises Private Limited
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Sanjeevani CO-OP Housing Society LTD
possession by Dec 2026 · Siddhartha Constructions
Sankalp Heights
possession by Dec 2027 · J K Realcon
Sankalp Residency Building NO A-1
declared completion Mar 2023 · Vighanhartha Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026