SAQLAINIA HEIGHTS

MASJID BUNDER STATION · MOHDYUSUF USMANGANI SHERAWALA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900015499

Delivery and registration

When is the project declared for completion?

SAQLAINIA HEIGHTS is registered with MahaRERA as P51900015499 and the promoter has declared completion for 30 Sep 2025.

30 Sep 2025

declared completion

12months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900015499
Registered on01 Mar 2018
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAQLAINIA HEIGHTS record 31 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAQLAINIA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
SAQLAINIA HEIGHTS1G+2130 Sep 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2021DUE TO SLOW SALE, MARKET CONDITIONS & DECLINE IN DEMAND OF PROPERTY
30 Sep 202130 Sep 2021WORK NOT COMPLETED YET
30 Sep 202130 Sep 2025The Project have extended the work on the 21st floor, in the Terrace, in the Overhead Water Storage Tank, extensions of 2 Lifts, Lift Machine room & 3rd Fire Evacuation Lift constr

Location, Land & Connectivity

Located at MASJID BUNDER STATION, SAMUEL STREET, Mumbai City, Mumbai City, 400009. Per the filed land record, the plot is bounded to the north by ADJ PLOT, to the south by ADJ PLOT, to the east by 60 FT SAMUEL STREET and to the west by ADJ PLOT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort3 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Powai / Hiranandani business park20 km
Andheri MIDC / SEEPZ20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mandvi

Inara
possession by Dec 2026 · M/S S Square Construction
Sauda Heights - Phase II
possession by Jun 2027 · MK India Enterprises
Aqdas Residency
possession by Dec 2027 · M/s. Alamdar Kapde Developer
Fatima Residency
possession by Dec 2027 · M K Enterprises
Hasan ALI
possession by Dec 2028 · Citymaker Builders Private Limited
Mustafa Arcade
possession by Jun 2030 · AAS Infra Construction

Other RERA-registered projects in Mumbai City

Saraswati Niwas
declared completion Apr 2026 · Sugee Twenty Three Developers LLP
Saraswati Sadan
declared completion Dec 2021 · S.s. Enterprise
Sarkars EL Dorado T1
possession by Jan 2030 · Chintaharni Chintpurni Realtors LLP
Saroj9
declared completion Sep 2025 · Sahaj Buildcon
Satguru Antop Hill
declared completion Jan 2023 · Newlook Constructions Pvt. Ltd
Sattva Sumera
possession by Dec 2031 · Alperton Developers AND Contractors Priv

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026