Mumbai/Project record

MahaRERA · the public record

SATGURU GARDEN

Mumbai Suburban · SHREE SATGURU DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

17 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

17 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008135

Delivery and registration

When is the project declared for completion?

SATGURU GARDEN is registered with MahaRERA as P51800008135 and the promoter has declared completion for 17 Jul 2022.

17 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008135
Registered on18 Aug 2017
Promoter-declared completion17 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SATGURU GARDEN record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shree Satguru Developers is the promoter of record on 12 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SATGURU GARDEN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
SATGURU GARDEN1G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court MumbaiTestamentary petition no 31/19971997Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered17 Jan 2022Due to Covid 19 Pandemic Situation

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400093. Per the filed land record, the plot is bounded to the north by Recreation Ground, to the south by 9 Mtr Wide DP Road, to the east by Park and to the west by slum. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~0 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ0 km
Powai / Hiranandani business park4 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Sale Bldg B1 Wing A B
possession by Dec 2026 · Accord Land Developers Pvt Ltd
Inspire Residency
possession by Dec 2026 · Sardar Realty
Mahakali Hills
possession by Dec 2026 · Mohid Construction Co
Royal Fantasy Phase II
possession by Dec 2026 · Royal Fantasy Constructions Private Limi
Samarth Enclave F AND G Wing Andheri Chhaya CHS
possession by Dec 2026 · Samarth Erectors AND Developers
Samarth Enclave H Wing Andheri Chhaya CHS
possession by Dec 2026 · Samarth Erectors AND Developers

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Satguru SRA Co-Op Hsg. Society
declared completion Dec 2025 · Surjit Bhojsingh Ailsinghani
Satgurus Kismet
possession by Dec 2027 · JGB Builders LLP
Satre Elite
possession by Jun 2028 · Ramchandra Vitthal Satre
Satre Happynest
possession by Dec 2027 · Satre Constructions LLP
Satwaratna Co Op Hsg Society Ltd
possession by Sep 2026 · Kishrajdevelopers
Satya Swaroop Chsl
declared completion Oct 2024 · Aadhunik Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026