Mumbai/Project record

MahaRERA · the public record

SATYAM BELLAGIO

SANPADA · Rajesh Dharamvir Gulati

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700014696

Delivery and registration

When is the project declared for completion?

SATYAM BELLAGIO is registered with MahaRERA as P51700014696 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700014696
Registered on26 Dec 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SATYAM BELLAGIO record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rajesh Dharamvir Gulati is the promoter of record on 6 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SATYAM BELLAGIO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+30.

BuildingWingsFloorsDeclared completion
SATYAM BELLAGI01G+3031 Jul 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SATYAM BELLAGIO, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250409420/11/2025Rajesh Dharamvir Gulati vs Mr Vinay Mahabal Kuckian lawful legal heir of Mr Mahabal Buba Kuckian and Mrs Hemavati M Kuckianorder passed

Location, Land & Connectivity

Located at SANPADA, SECTOR 8, Thane, Thane, 400705. Per the filed land record, the plot is bounded to the north by PLOT NO 14, to the south by 15 M ROAD, to the east by 15 M WIDE ROAD and to the west by PLOT NO 16. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park13 km
Bandra Kurla Complex (BKC)15 km
Chhatrapati Shivaji Int'l Airport16 km
Andheri MIDC / SEEPZ17 km
Lower Parel / Worli business district20 km
Nariman Point / Fort25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rajesh Dharamvir Gulati is the promoter on 6 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Rajesh Dharamvir Gulati

Rajesh Dharamvir Gulati
Past its declared completion dateThane
Rajesh Dharamvir Gulati
FlaggedRaigarh
Rajesh Dharamvir Gulati
Not filing quarterly progress reportsRaigarh

Other RERA-registered projects in Sanpada

ONE Akshar
possession by Dec 2026 · Akshar Realtors
Raheja Solaris-1
possession by Dec 2026 · Raheja Universal Ltd.
BUL BUL CO-Operative Housing Society Limited
possession by Dec 2026 · Ashwiniinfradevelopments Private Limited
Gami Terra
possession by Dec 2026 · LAL Gebi Infra Private Limited
Satyam Altura
possession by Dec 2026 · Satyam Lifescapes LLP
Tricity Montview
possession by Dec 2026 · Tricity Realty LLP

Major developers building in Sanpada

Other RERA-registered projects in Thane

Satyam Chopra Enclave
possession by Mar 2027 · SAI Satyam Properties LLP
Satyam Dwarka
possession by Dec 2030 · Satyam Superstructures Private Limited
Satyam Oleander
declared completion Dec 2024 · M/S Bhoir Buildcon
Satyam Seasons
possession by Dec 2027 · Satyam Lifescapes LLP
Satyam Sheela Wing F
declared completion Jul 2026 · Shreeji Developers
Satyam Sicilia
possession by Dec 2028 · Sunny Home Makers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026