MahaRERA Property Intelligence · Thane

SBM CLASSIQUE

P51700021977 · THANE WEST · promoter Sbm Developers Pvt

Certificate SignedDue 31 Jul 2025

Delivery & Registration

MahaRERA registrationP51700021977
Registered on25 Aug 2019
Promoter-declared completion31 Jul 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
SBM CLASSIQUE1G+1831 Jul 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at THANE WEST, TEEN HATH NAKA, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by 78 A 1 M G ROAD, to the south by CS NO 72, to the east by C S NO 59 and to the west by C S NO 73. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Naupada

Veer Galaxy
possession by Jul 2026 · Yash Infra
Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty

Major developers building in Naupada

Other RERA-registered projects in Thane

SBM SKY
possession by Dec 2027 · SBM Developers PVT LTD
SD Empire
declared completion Jun 2025 · Empire Developers
SD Galaxy
possession by Dec 2027 · Someshwarnath Developers & Builders
SEA Green
possession by Mar 2029 · Sierra Infraproject LLP
SEA Green Apartment
declared completion Dec 2022 · Aakash Builders & Developers
SEA Green Aurus
possession by Feb 2027 · Sea Green Homes

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026