MahaRERA Property Intelligence · Thane

SEASONS PARK

P51700017459 · AMBERNATH · promoter Shree Balaji Homes

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700017459
Registered on13 Aug 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
TOWER 11G+1231 Dec 2021
TOWER 21G+1231 Dec 2021
TOWER 31G+1231 Dec 2021
TOWER 41G+1231 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at AMBERNATH, S NO 49 H NO 4/A, 4/B, 6/D, 6E, Kalyan, Thane, 421501. Per the filed land record, the plot is bounded to the north by GARDEN 184 AND S NO 49 H NO 3, to the south by SURVEY NO 49 BY 6 P AND PIPELINE ROAD, to the east by SURVEY NO 66 and to the west by SURVEY NO 49 BY 4 BY C. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Balaji Homes is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shree Balaji Homes

Shree Balaji Homes
Past its declared completion dateThane
Shree Balaji Homes
Not filing quarterly progress reportsPalghar

Other RERA-registered projects in Ambernath

24 High Bizbay
possession by Jul 2026 · Apex Infra
Shree Gajanan Enterprises Rukhmini CHS
possession by Jul 2026 · Shree Gajanan Enterprises Rukhmini CHS
Walekar Homes
possession by Aug 2026 · Walekar & Son's Developers
Patels Eirene
possession by Aug 2026 · Pramukh Developers
Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters

Major developers building in Ambernath

Other RERA-registered projects in Thane

Seasons Pearl
possession by Dec 2029 · Mahadev SAI Homes LLP
Seasons Saffron
possession by Dec 2026 · Seasons SAI Developers
Seasons Sahara
declared completion Dec 2023 · Samarth SAI Builders & Developers
Seasons Sahara Building NO. 1
possession by Dec 2028 · Samarth SAI Builders & Developers
Seasons Sahara Building NO 2
declared completion Dec 2024 · Samarth SAI Builders & Developers
Seasons Sahara Nano Building NO A And B
possession by Dec 2026 · Samarth SAI Builders & Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026