MahaRERA Property Intelligence · Mumbai City

SHANDILYA VILLA

P51900007512 · Worli Sea Face · promoter Shandilya Properties Llp

Certificate SignedDue 01 Jan 2023

Delivery & Registration

MahaRERA registrationP51900007512
Registered on17 Aug 2017
Promoter-declared completion01 Jan 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35.

BuildingWingsFloorsDeclared completion
SHANDILYA VILLA1G+3501 Jan 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
01 Jan 202301 Jan 2023The Building comprised in the Project is almost complete. The delay is only on account of the pandemic of CoVid 19 and the reverse migration of skilled and unskilled labour as a c

Location, Land & Connectivity

Located at Worli Sea Face, Khan Abdul Guffar Khan Road, Ward GSouth, Mumbai City, 400030. Per the filed land record, the plot is bounded to the north by By Property bearing CS No 735, to the south by By Property bearing CS No 736 , to the east by By Property bearing CS No 767A and 766 and to the west by By Moulana Abdul Gaffar Khan Road . Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)8 km
Nariman Point / Fort10 km
Chhatrapati Shivaji Int'l Airport10 km
Andheri MIDC / SEEPZ14 km
Powai / Hiranandani business park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Worli

Marina BAY Worli SEA Face
possession by Sep 2026 · Saumya Buildcon Pvt Ltd
Aakasa
possession by Dec 2027 · Techno Freshworld LLP
Redevelopment Project OF Dayawani Chawl
possession by Dec 2027 · Anil Murarilal Agarwal
Birla Niyaara Phase-1
possession by Mar 2028 · Aditya Birla Real Estate Limited
Birla Niyaara Phase-2
possession by Mar 2029 · Aditya Birla Real Estate Limited
Sea Krest
possession by Dec 2029 · Sugee Developers Pvt. Ltd.

Major developers building in Worli

Other RERA-registered projects in Mumbai City

Shankesh Crown
possession by Dec 2026 · H. Mehta Realtors LLP
Shankheshwar Heights
possession by Jun 2027 · Siddheshwar Construction Co.
Shanta Durga
declared completion Dec 2024 · Nine Dimensions Housing LLP
Shanta Nivas
declared completion Dec 2017 · Sunrise Developers
Shantadurga
declared completion Jan 2023 · Lakshmi Builders AND Developers
Shanti Harbour Crest
declared completion Jun 2026 · Ojus Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026