MahaRERA · the public record
Birla Niyaara Phase-1
Lower Parel · Aditya Birla Real Estate Limited
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Mar 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51900031916
Delivery and registration
When is the project declared for completion?
Birla Niyaara Phase-1 is registered with MahaRERA as P51900031916 and the promoter has declared completion for 31 Mar 2028.
31 Mar 2028
declared completion
18months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51900031916 |
| Registered on | 22 Nov 2021 |
| Promoter-declared completion | 31 Mar 2028 |
| Current status | Certificate Signed |
| Against today | 18 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Birla Niyaara Phase-1 record 16 quarterly progress reports since registration.
16quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In Birla Niyaara Phase-1, ₹569.20 Cr of a declared ₹1083.43 Cr estimated project cost is reported as incurred, about 52.5%, as at the last certified filing with MahaRERA.
52.5%
₹569.20 Cr
of ₹1083.43 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Birla Niyaara Phase-1, 400 of 414 homes filed with MahaRERA are recorded as sold or booked, about 97%, and 14 remain available.
97%sold
400 of 414 homes
₹3012.75 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹1918.78 Cr (about 64%) is recorded as collected and ₹1093.98 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 400 registered agreements, the effective carpet rate is ₹54,018/sqft, with eight in ten falling between ₹48,103 and ₹71,763 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 3 | TA-P304 | 852 sqft (79.15 sqm) | ₹2.97 Cr |
| Floor 3 | TA-P305 | 1,203 sqft (111.75 sqm) | ₹4.26 Cr |
| Floor 3 | TA-P306 | 851 sqft (79.05 sqm) | ₹2.97 Cr |
| Floor 4 | TA-P404 | 852 sqft (79.15 sqm) | ₹2.97 Cr |
| Floor 4 | TA-P405 | 1,203 sqft (111.75 sqm) | ₹4.26 Cr |
| Floor 4 | TA-P406 | 851 sqft (79.05 sqm) | ₹2.97 Cr |
| Floor 5 | TA-P504 | 852 sqft (79.15 sqm) | ₹3.11 Cr |
| Floor 5 | TA-P506 | 851 sqft (79.05 sqm) | ₹3.11 Cr |
| Floor 68 | TA-6801 | 3,744 sqft (347.85 sqm) | ₹18.79 Cr |
| Floor 70 | TA-7001 | 3,744 sqft (347.85 sqm) | ₹18.79 Cr |
| Floor 72 | TA-7201 | 3,744 sqft (347.85 sqm) | ₹18.79 Cr |
| Floor 74 | TA-7401 | 3,744 sqft (347.85 sqm) | ₹18.79 Cr |
| Floor 76 | TA-7601 | 10,296 sqft (956.5 sqm) | ₹50.26 Cr |
| Floor 76 | TA-7602 | 11,914 sqft (1106.85 sqm) | ₹58.19 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 18 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 400 homes carry one, and 14 of the 414 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| TA-P304 | 852 sqft | Rs 4.4430 cr typical, over Rs 3.7210 cr to Rs 8.2661 cr | 164 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Birla Niyaara Phase-1, 6 of the 14 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+86 and 414 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Tower A | 1 | G+86 | 414 | - |
Unit mix on the filing: 414 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Lower Parel, Pandurang Budhkar Marg, Ward GSouth, Mumbai City, 400030. Per the filed land record, the plot is bounded to the north by 22 m Wide DP Road, to the south by Pandurang Budhkar Marg, to the east by Bombay Dyeing Mills and to the west by CS No 793 and 1 of 794. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Lower Parel / Worli business district | 1 km |
| Bandra Kurla Complex (BKC) | 8 km |
| Nariman Point / Fort | 9 km |
| Chhatrapati Shivaji Int'l Airport | 10 km |
| Andheri MIDC / SEEPZ | 14 km |
| Powai / Hiranandani business park | 15 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.