Mumbai/Project record

MahaRERA · the public record

SHANTA MANGESH APARTMENT

Andheri West · SHANTA MANGESH DEVELOPERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006170

Delivery and registration

When is the project declared for completion?

SHANTA MANGESH APARTMENT is registered with MahaRERA as P51800006170 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006170
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHANTA MANGESH APARTMENT record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shanta Mangesh Developers is the promoter of record on 66 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

66projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHANTA MANGESH APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
SHANTA MANGESH1G+19-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 4 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court Dindoshi1169 of 20082008Pending
City Civil Court Dindoshi1170 of 20082008Pending
High Court Of Bombay11315 of 20162016Pending
High Court Of Bombay1476 of 20172017Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Sudden hospitalization, Mr Vijay Shridhar Mallya, Director of the Promoter, on account of severe illness led to halting of business operations and inability to generate funds for t

Location, Land & Connectivity

Located at Andheri West, Andheri, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by LAND BEARING CTS 159A, to the south by LAND BEARING CTS 96 AND 97, to the east by BY 90ft WIDE HINDU FRIENDS SOCIETY ROAD and to the west by LAND BEARING CTS 159A AND PARTLY BY ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park6 km
Bandra Kurla Complex (BKC)8 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya
La Alteza
possession by Dec 2026 · Emerald Developers

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Shanti
possession by Jul 2027 · S.k. Realtors
Shanti Niketan
declared completion Oct 2020 · Matrix Constructions
Shanti Sadan
declared completion Dec 2017 · MAN Global Ltd.
Shanti Sadan
possession by Dec 2026 · Shree Hans Realtors LLP
Shantiniketan
declared completion May 2025 · Namorealty AND Infra LLP
Shantiniketan 2 CHS LTD
declared completion Nov 2020 · S D Bhalerao Constructions PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026