Mumbai/Project record

MahaRERA · the public record

SHANTI NIKETAN

Mumbai Suburban · MATRIX CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008789

Delivery and registration

When is the project declared for completion?

SHANTI NIKETAN is registered with MahaRERA as P51800008789 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008789
Registered on19 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHANTI NIKETAN record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Matrix Constructions is the promoter of record on 30 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

30projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHANTI NIKETAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
SHANTI NIKETAN1G+19-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SHANTI NIKETAN, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001202420/11/2017Darshan Mohan Tawde vs PAWAN ASHOK THARWANIorder passed
CC00600000010035101/08/2019Manisha Hitendra Varale vs Matrix Constructionsorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Change of planning authority from MCGM to MHADA

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400083. Per the filed land record, the plot is bounded to the north by BLDG NO 15, to the south by BLDG NO 13, to the east by 12 20 MT WIDE ROAD and to the west by EASTERN EXP HIGHWAY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport2 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Matrix Constructions is the promoter on 6 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Matrix Constructions

Matrix Constructions
FlaggedMumbai Suburban
Matrix Constructions
FlaggedMumbai Suburban
Matrix Constructions
FlaggedMumbai Suburban
Matrix Constructions
FlaggedMumbai Suburban

Other RERA-registered projects in Vikhroli East

Shree Balaji 7
possession by Sep 2026 · Saptrishi Landmarks LLP
Unique Enclave Residency
possession by Sep 2026 · Fazal Shaikh
Vrindavan Elite
possession by Oct 2026 · Matrix Constructions
Meadows 83
possession by Oct 2026 · Shreeji Realtors
Eastern Groves Phase 2
possession by Dec 2026 · VL Savli Developers LLP
GS Casa
possession by Dec 2026 · Prach Realcon LLP

Major developers building in Vikhroli East

Other RERA-registered projects in Mumbai Suburban

Shanti Sadan
declared completion Dec 2017 · MAN Global Ltd.
Shanti Sadan
possession by Dec 2026 · Shree Hans Realtors LLP
Shantiniketan
declared completion May 2025 · Namorealty AND Infra LLP
Shantiniketan 2 CHS LTD
declared completion Nov 2020 · S D Bhalerao Constructions PVT LTD
Sharanya
possession by Dec 2026 · M/S Satsang Enterprises
Sharda Heights
declared completion Dec 2018 · Narendra Jagdishprasad Agarwal

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.