MahaRERA Property Intelligence · Thane
P51700003655 · MAJIWADA · promoter Sheth Developers Private
| MahaRERA registration | P51700003655 |
| Registered on | 06 Aug 2017 |
| Promoter-declared completion | 31 Dec 2027 |
| Current status | Certificate Signed |
| Against today | 17 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Sheth Developers Private is the promoter of record on 65 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
MahaRERA's cost filing puts construction at ~63.2% of the estimated project cost incurred as of the last certificate (₹104.41 Cr spent against a ₹165.20 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 246 homes filed with MahaRERA, 179 are sold/booked (164 with registered agreements + 15 booked) and 67 remain available (~73% sold) — selling steadily. Buyers have committed ₹283.46 Cr in agreement value so far. Of that, ₹200.14 Cr (~71%) is already collected, ₹83.32 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 179 registered agreements, the effective carpet rate is ₹16,380/sqft (typical range ₹9,241–₹22,066) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35 and 246 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| FERN | 1 | G+35 | 116 | - |
| GLADE | 1 | G+35 | 130 | - |
Unit mix on the filing: 246 residential.
29 complaints are on the MahaRERA record for this project, with orders passed in 29. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000023107 | 01/02/2018 | Milind Patil vs Sheth Developers Pvt Ltd | order passed |
| CC006000000057082 | 13/02/2019 | N C Paul vs Sheth Develpers Pvt Ltd. | order passed |
| CC006000000079359 | 23/05/2019 | PRASHANT GOREGAONKAR AND ANOTHER vs SHETH DEVELOPERS | order passed |
| CC006000000079420 | 24/05/2019 | MRS. SUNITA RAVI AHUJA AND ANR vs M/S. SHETH DEVELOPERSPVT. LTD. | order passed |
| CC006000000079425 | 26/05/2019 | MR. AASHUTOSH PARASHURAM MALSHE AND ANR vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079426 | 24/05/2019 | MR. ASHOK J. PATEL AND ANR vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079427 | 25/05/2019 | MR. KIRAN B. NAGAPURKAR AND ANR vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079429 | 25/05/2019 | MR. VASHU S. KESWANI AND ANR vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079431 | 25/05/2019 | MR. SATISH MAHADEV TENGERI AND ANR vs M/S SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079432 | 25/05/2019 | MR. VISHAL SUDHAKAR ADAWADKAR AND ANR vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079433 | 25/05/2019 | MRS. SHALINI RAJARAM PATIL AND ORS vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079434 | 25/05/2019 | MR. HEMANT RAMESH BONDE AND ANR vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079435 | 25/05/2019 | MR. HEMANT RAMESH BONDE AND ANR vs M/S SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079445 | 24/05/2019 | MR. MANOHAR NARAYAN IYER AND ANR vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079447 | 25/05/2019 | MRS. CHITRA SUNIL CHAUDHARY AND ORS vs M/S. SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000079448 | 25/05/2019 | MR. KRISHNA R. SOLANKI AND ANR vs M/S SHETH DEVELOPERS PVT. LTD. | order passed |
| CC006000000199098 | 21/11/2021 | VINIT RAJARAM SARANGDHAR vs SHETH DEVELOPERS PVT LTD | order passed |
| CC006000000199314 | 06/12/2021 | ASHOK J PATEL vs SHETH DEVELOPERS | order passed |
| CC006000000199328 | 07/12/2021 | AASHUTOSH MALSE vs SHETH DEVELOPERS | order passed |
| CC006000000199329 | 07/12/2021 | MRS SHALINI R PATIL vs SHETH DEVELOPERS | order passed |
| CC006000000199341 | 08/12/2021 | VISHAL ADAWAKAR vs sheth developers | order passed |
| CC006000000199342 | 08/12/2021 | PRAVIN K SOLANKI vs SHETH DEVELOPERS | order passed |
| CC006000000199345 | 08/12/2021 | KIRAN B NAGAPURKAR vs SHETH DEVELOPERS | order passed |
| CC006000000209356 | 09/12/2021 | SUNITA R AHUJA vs sheth developers | order passed |
| CC006000000209364 | 10/12/2021 | SATISH M TENGERI vs SHETH DEVELOPERS | order passed |
| CC006000000209369 | 11/12/2021 | PRASHANT GOREGOANKAR vs SHETH DEVELOPERS | order passed |
| CC006000000209483 | 21/12/2021 | HEMANT BONDE vs SHETH DEVELOPERS | order passed |
| CC006000000209486 | 21/12/2021 | HEMANT BONDE vs SHETH DEVELOPERS | order passed |
| CC006000000375108 | 04/04/2023 | Vikash Kumar vs Sheth Developers Private Limited | order passed |
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay High Court | WP/8647/2024 | 2024 | Ongoing |
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Dec 2025 | 31 Dec 2025 | 1) After registration of the said Project with MahaRERA vide letter dated 05.03.2020 Thane Municipal Corporation has given stop work notice and had stopped further development of t |
| 30 Dec 2023 | 31 Dec 2027 | As per order of the Hon'ble Chairman (MahaRERA) Dated 12/12/2025 we request you kindly to grant us extension till 31/12/2027 |
Located at MAJIWADA, EASTERN EXPRESS HIGHWAY POKHARAN RD NO 2, Andheri, Mumbai Suburban, 400610. Per the filed land record, the plot is bounded to the north by 20 METER WIDE DP ROAD, to the south by EXISTING NALLA, to the east by EASTERN EXPRESS HIGHWAY and to the west by 12 METER WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 13 km |
| Andheri MIDC / SEEPZ | 14 km |
| Chhatrapati Shivaji Int'l Airport | 18 km |
| Bandra Kurla Complex (BKC) | 20 km |
| Lower Parel / Worli business district | 28 km |
| Nariman Point / Fort | 35 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in SHETH VASANT LAWNS?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Sheth Developers Private Limited is the promoter on 9 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
See every Sheth Developers Private Limited project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026