SHIV ARCADE

DRONAGIRI · SHIV CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000015464

Delivery and registration

When is the project declared for completion?

SHIV ARCADE is registered with MahaRERA as P52000015464 and the promoter has declared completion for 30 Jan 2024.

30 Jan 2024

declared completion

32months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000015464
Registered on27 Feb 2018
Promoter-declared completion30 Jan 2024
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIV ARCADE record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHIV ARCADE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
SHIV ARCADE1G+1431 Jan 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SHIV ARCADE, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240098102/12/2024SHYAM PRAKASH PANDEY vs SHIV CONSTRUCTIONSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jan 2024In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas

Location, Land & Connectivity

Located at DRONAGIRI, PLOT NO 34 SECTOR 47, Panvel, Raigarh, 400707. Per the filed land record, the plot is bounded to the north by 15 Mtrs WIDE ROAD, to the south by PLOT NO 31, to the east by PLOT NO 33B and to the west by PLOT NO 33A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort16 km
Lower Parel / Worli business district20 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport27 km
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shiv Constructions is the promoter on 6 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Dronagiri

Pramukh Dharma
possession by Sep 2026 · Pramukh Associates
Vaastu Ankita
possession by Sep 2026 · Vaastu Builders & Developers
OM Shakti Enclave
possession by Dec 2026 · OM Shakti Enterprises
Vaishnavi Emperia
possession by Nov 2027 · RK Group OF Infra
Villa Oceano
declared completion Dec 2025 · Shreeji Creations
Lakhani Grandeur
declared completion Oct 2025 · Lakhani Builders PVT LTD

Other RERA-registered projects in Raigarh

Shiv Arya
declared completion Jul 2023 · Shiv Realtors
Shiv Avani
possession by Dec 2028 · Shiv Shakti Buildcon
Shiv Bliss
possession by Mar 2027 · Shankar Shimgya Patil
Shiv Bliss
declared completion Dec 2022 · Shivkrupa Buildcon
Shiv Castle
declared completion Jun 2022 · Sunil Shankar Bhosle
Shiv Complex Building
declared completion May 2023 · Laxmi Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026