Mumbai/Project record

MahaRERA · the public record

SHIVAALIK PARK

BHIWANDI · SUN REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

127units filed as unsoldInventory · 18 September 2026
20 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

20 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700023966

Delivery and registration

When is the project declared for completion?

SHIVAALIK PARK is registered with MahaRERA as P51700023966 and the promoter has declared completion for 20 Dec 2025.

20 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700023966
Registered on14 Jan 2020
Promoter-declared completion20 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIVAALIK PARK record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 679 homes carry one, and 127 of the 806 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1-A-003322 sqftRs 14.98 lakh420 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SHIVAALIK PARK, 117 of the 127 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 126 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHIVAALIK PARK BLDG 11G+4-
SHIVAALIK PARK BLDG 21G+4-
SHIVAALIK PARK BLDG 31G+4-
SHIVAALIK PARK BLDG 41G+4-
SHIVAALIK PARK BLDG 51G+4-
SHIVAALIK PARK BLDG 61G+4-
SHIVAALIK PARK BLDG 71G+4-
SHIVAALIK PARK BLDG 81G+4-
SHIVAALIK PARK BLDG 91G+4-
SHIVAALIK PARK BLDG 101G+4-
SHIVAALIK PARK BLDG 111G+4-
SHIVAALIK PARK BLDG 121G+4-
SHIVAALIK PARK BLDG 131G+4-
SHIVAALIK PARK BLDG 141G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered20 Dec 2024Due to hospitalization of one of our promoter due to serious health issue, rising cost of construction materials and shortage of labour there is a delay is completion work.
20 Dec 202420 Dec 2025OUR PROJECT CONSIST OF 1 TO 14 BUILDING.OUT THEESE BUILDING ONLY 2 BUILDING OC IS PENDING AND REST FOR 12 BUILDING OC IS RECEIVED ON TIME. THEREFORE WE WANT TO APPLY FOR EXTENSIN T

Location, Land & Connectivity

Located at BHIWANDI, BHADWAD , Bhiwandi, Thane, 421302. Per the filed land record, the plot is bounded to the north by SNO 73P AND 80P, to the south by SNO 80P AND 76, to the east by 18M DP ROAD and to the west by BHADWAD ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park26 km
Andheri MIDC / SEEPZ28 km
Chhatrapati Shivaji Int'l Airport31 km
Bandra Kurla Complex (BKC)33 km
Lower Parel / Worli business district41 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SUN Realtors is the promoter on 5 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SUN Realtors

SUN Realtors
Past its declared completion datePalghar
SUN Realtors
Not filing quarterly progress reportsPalghar

Other RERA-registered projects in Bhiwandi

Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Anantam Heights
possession by Oct 2026 · Kanak Realty
Upper Thane - Woodlands A, B AND J
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Shivaay Avyaan
declared completion Jun 2026 · Shreeram Buildcon
Shivaay Fortune
possession by Jun 2028 · Shreeram Infra
Shivalay
possession by Sep 2027 · Yuvvraj Constructions
Shivalay
possession by Jun 2027 · Phoenix Infra
Shivalaya
possession by Dec 2029 · Shree Shivay Developers
Shivalaya Heights
possession by Sep 2027 · S R Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026