Mumbai/Project record

MahaRERA · the public record

SHREE PARSHWANATH SRA CHS LTD

Bhandup west · Chintamani Realtors

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009968

Delivery and registration

When is the project declared for completion?

SHREE PARSHWANATH SRA CHS LTD is registered with MahaRERA as P51800009968 and the promoter has declared completion for 31 Mar 2024.

31 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009968
Registered on23 Aug 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE PARSHWANATH SRA CHS LTD record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Chintamani Realtors is the promoter of record on 53 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

53projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE PARSHWANATH SRA CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
Sale wing A1G+2431 Mar 2020
Rehab wing B1G+1831 Dec 2020
Rehab wing C1G+731 May 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2024The building is ready for occupation. The possession for Furniture and fixtures has been already given to Allotee members. We are under process of obtaining CFO Completion and Road

Location, Land & Connectivity

Located at Bhandup west , Bhattipada Road, Kurla, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by CHANDRADHAN CHS, to the south by NATIONAL SCHOOL, to the east by BHATTIPADA ROAD and to the west by ANAND MANGAL CHS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Primo
possession by Sep 2026 · Ceear Land Developers LLP
Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing C
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Shree Pinal Project A
declared completion Nov 2025 · Pinal Realty LLP
Shree Pinal Project B
possession by Nov 2027 · Pinal Realty LLP
Shree Prafull Chsl
declared completion Sep 2023 · Shree Shyam Developers
Shree Pranam
possession by Dec 2029 · Meghna Infracon Infrastructure Limited
Shree Raam Residency
possession by Jun 2028 · Antariksh Developers
Shree Radhe Shyam Heights
possession by Dec 2027 · Shree SAI Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026