Shree Swami Samartha Darshan

Mahim · Shree Sai Datta Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900009258

Delivery and registration

When is the project declared for completion?

Shree Swami Samartha Darshan is registered with MahaRERA as P51900009258 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900009258
Registered on22 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shree Swami Samartha Darshan record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shree Swami Samartha Darshan in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
Shree Swami Samartha Darshan1G+2110 Jun 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered09 Jun 2020We had applied for NOC from MMRDA. We submitted plans and other documents / papers to MMRDA as and when asked by MMRDA. MMRDA took more than six months to issue us their NOC. Also,
09 Jun 202030 Jun 2021Due to this COVID-19 pandemic situation and non availability of the labours and materials till 1st November 2020 on our Shivaji Park site which is registered under MAHARERA No. P51

Location, Land & Connectivity

Located at Mahim, Lady Jamshedji road, Mumbai City, Mumbai City, 400016. Per the filed land record, the plot is bounded to the north by Plot No 51 and 52, to the south by Bai Padmabi Thakkar Road, to the east by Plot No 57 and to the west by Lady Jamshedji Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Lower Parel / Worli business district5 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park11 km
Nariman Point / Fort13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Sai Datta Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shree Sai Datta Developers

Shree Sai Datta Developers
FlaggedMumbai City

Other RERA-registered projects in Mahim

Makhdoom Heights
possession by Nov 2026 · Naqi Developers Private Limited
Karpur Heights
possession by Dec 2026 · Parvasha Grihnirman Sanstha
ANJ Ananda
possession by Dec 2026 · A N J Recon LLP
Kapil Tirth
possession by Dec 2026 · Prathamesh Projects LLP
Moin Heights
possession by Dec 2026 · Mansoor Mehmood Sayyed
Royal Heights
possession by Dec 2026 · S.a. Enterprises

Major developers building in Mahim

Other RERA-registered projects in Mumbai City

Shree Udyan
possession by Dec 2026 · Square Nine Habitats LLP
Shree Vigneshwar CO-Operative Housing Society
declared completion Dec 2021 · Bineeta
Shreeji Heights
possession by Dec 2030 · Anupam Creation
Shreeji Palazzo
possession by Dec 2026 · Excellent Enterprise
Shreeji Serenity
possession by Mar 2028 · Space Infra
Shreeji Towers
possession by Sep 2027 · Neumec Developer AND Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.