MahaRERA Property Intelligence · Mumbai Suburban

SHRI YAMAI KRUPA

P51800014999 · BORIWALI · promoter Jeevandeep Developers

Certificate SignedDue 30 Oct 2022

Delivery & Registration

MahaRERA registrationP51800014999
Registered on22 Jan 2018
Promoter-declared completion30 Oct 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Jeevandeep Developers is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
SHRI YAMAI KRUPA1G+1931 Mar 2018

Complaints & Orders

6 complaints are on the MahaRERA record for this project, with orders passed in 6. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000007910102/05/2019Clifford Theodore Dsouza, vs Jeevandeep developers, Bhuvanesh Warde, Uday Rawool, Narayan Warde, Vasant Rawool, Deepa Warde & Orsorder passed
CC00600000007927017/05/2019Rohan Lobo vs M/s Jeevandeep Developers, Bhuvanesh Warde, Uday Rawool, Narayan Warde, Vasant Rawool, Deepa Warde,order passed
CC00600000019627617/03/2021VASANTMADHAV GANSHYAM KUDWA vs JEEVANDEEP DEVELOPERSorder passed
CC00600000019642311/08/2021MEGAN OLIVERIA vs JEEVANDEEP DEVELOPERS & ORSorder passed
CC00600000019651011/08/2021MARIA HILLARINA ALVES vs JEEVANDEEP DEVELOPERSorder passed
CC00600000019719511/08/2021ROSEMARY LOBO vs JEEVANDEEP DEVELOPERS & ORSorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 201830 Oct 2022The Project Comprises of one building. The Work has been delayed due to Non-payment from flat purchases and pending approvals from competent authorities. We are in the process of c
31 Mar 201831 Mar 2019WE HAD OBTAINED RERA REGISTRATION FOR SHRI YAMAI KRUPA PROJECT UNDER P51800014999 DATED 22.01.2018 AND REGISTRATION AS VALID TILL ATE 31.03.2018 BUT DUE TO WORK HAS BEEN DELAYED DU

Location, Land & Connectivity

Located at BORIWALI, MAHARASHTRA, Borivali, Mumbai Suburban, 400016. Per the filed land record, the plot is bounded to the north by F P 459-A, to the south by F P 464, to the east by F P 461 AND 462 and to the west by PITAMBAR LANE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Jeevandeep Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Jeevandeep Developers

Jeevandeep Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Mahim

Makhdoom Heights
possession by Nov 2026 · Naqi Developers Private Limited
Karpur Heights
possession by Dec 2026 · Parvasha Grihnirman Sanstha
Airyaman Terraces
possession by Dec 2026 · Airyaman Developers LLP
ANJ Ananda
possession by Dec 2026 · A N J Recon LLP
Kapil Tirth
possession by Dec 2026 · Prathamesh Projects LLP
Medius
possession by Dec 2026 · Aventa Properties LLP

Major developers building in Mahim

Other RERA-registered projects in Mumbai Suburban

Shriji Heritage
declared completion Dec 2025 · Shriji Apartments CO-Operative Housing S
Shrikant Chembers II
declared completion Mar 2023 · Shrikant Studios Pvt. Ltd.
Shrim
possession by Jun 2027 · Shrim Co-Operative Housing Society
Shriniketan
possession by Dec 2026 · Arham Realty
Shriram Niwas
possession by Jun 2027 · Sarvshubh Enterprises
Shrirang
declared completion Jun 2022 · Virendra Natwarlal Sheth

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026