MahaRERA Property Intelligence · Thane

SHUBH NIRMAN PHASE II

P51700023746 · BELAVALI · promoter Guru Developers

Certificate SignedDue 30 May 2023

Delivery & Registration

MahaRERA registrationP51700023746
Registered on03 Jan 2020
Promoter-declared completion30 May 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
WING E1G+431 May 2022
WING F1G+431 May 2022
WING G1G+431 May 2022
WING H1G+431 May 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BELAVALI, BEHIND ALLAHABAD BANK, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by SR 17 3C HSN 17 2 SNO 21, to the south by CENTRAL RAILWAY LAND, to the east by HSNO19 2 and to the west by ROAD 9MW. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Guru Developers is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Guru Developers

Guru Developers
Past its declared completion dateThane

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Shubh Nisarg
declared completion Dec 2021 · Vardhaman AND Vastu Associates
Shubh Shantai Residency
possession by Dec 2027 · Shubh Vastu Develeopers
Shubh Shrushti LM
possession by Dec 2028 · Vinayak Enterprises
Shubh Srushti
declared completion Oct 2018 · Vinayak Enterprises
Shubh Srushti Phase II
declared completion Dec 2023 · Vinayak Enterprises
Shubh Srushti Phase III
declared completion May 2025 · Vinayak Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026