Mumbai/Project record

MahaRERA · the public record

SHUBHAM

Mumbai Suburban · ADITYA ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010791

Delivery and registration

When is the project declared for completion?

SHUBHAM is registered with MahaRERA as P51800010791 and the promoter has declared completion for 30 Nov 2021.

30 Nov 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010791
Registered on31 Aug 2017
Promoter-declared completion30 Nov 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHUBHAM record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHUBHAM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
TILAK NAGAR SHUBHAM CHSL1G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 May 202110% work is pending and also noc is pending from other work

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400089. Per the filed land record, the plot is bounded to the north by BUILDING NO 65, to the south by SCHOOL, to the east by BUILDING NO 67 and to the west by PG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district11 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aditya Associates is the promoter on 14 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Aditya Associates project & its RERA track record →

Other flagged projects by Aditya Associates

Aditya Associates
Past its declared completion dateMumbai Suburban
Aditya Associates
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Chembur

Orient Regency Building No. 1
possession by Dec 2026 · Orient Combine
Sree Sudarshan Heights
possession by Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
possession by Dec 2026 · Chinnaiah Venkatesh Gowda
Promesa Midtown
possession by Dec 2026 · Darshan Properties
Vishwasangam
possession by Dec 2026 · Vishwashakti Cooperative Housing Society
Ampple-ONE
possession by Mar 2027 · Amppletech Projects Private Limited

Other RERA-registered projects in Mumbai Suburban

Shubham Alaska
declared completion Jun 2025 · Dipal Laxmichand Shah
Shubham Artesia
possession by Dec 2027 · Avvad Realtty LLP
Shubham Origins
possession by Dec 2029 · Cadcons Developers LLP
Shubhamkaroti Aarambh
possession by Dec 2027 · Shubhamkaroti Infratech LLP
Shyam Kutir
possession by Feb 2028 · Spacewalk Realty LLP
Sianna Heights
declared completion Jun 2026 · Shubhjivan Builders PVT LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026