MahaRERA Property Intelligence · Mumbai Suburban

Srushti Enclave

P51900011095 · Chembur · promoter Gadkari Builders Associates

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP51900011095
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Gadkari Builders Associates is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~100.5% of the estimated project cost incurred as of the last certificate (₹42.36 Cr spent against a ₹42.15 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 30 homes filed with MahaRERA, 30 are sold/booked (28 with registered agreements + 2 booked) and 0 remain available (~100% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹34.21 Cr in agreement value so far. Of that, ₹22.37 Cr (~65%) is already collected, ₹11.84 Cr receivable — a read on how far along these sales really are. Note: the project registers 59 homes in total, but this sold/unsold inventory filing covers only 30 of them — the other 29 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 30 registered agreements, the effective carpet rate is ₹14,395/sqft (typical range ₹9,145–₹33,870) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

⚠ The inventory filing also declares: 5 reserved and 10 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 59 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Srushti Enclave1G+155931 Dec 2019

Unit mix on the filing: 59 residential.

Complaints & Orders

12 complaints are on the MahaRERA record for this project, with orders passed in 12. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002343721/02/2018LEKHARAJAU VENKATA NAGARAJA RAO vs M/S Gadkari Builders and Associatesorder passed
CC00600000000176320/11/2017Durgaprasad Gundopant Tambulwadkar vs Gadkari Builders & Associatesorder passed
CC00600000005614210/09/2018Shrikrishna Kulkarni vs Gadkari Builder and Associatesorder passed
CC00600000005615310/09/2018Amit Saxena vs Gadkari Builder and Associatesorder passed
CC00600000005615510/09/2018Pallavi Otawkar vs Gadkari Builder and Associatesorder passed
CC00600000005615910/09/2018Asavari Otawkar vs Gadkari Builder and Associatesorder passed
CC00600000005616010/09/2018Sameer Walishetty vs Gadkari Builder and Associatesorder passed
CC00600000005622416/09/2018Basawantray Shivappa Hampanagoudur vs Gadkari Builder and Associatesorder passed
CC00600000005635827/09/2018Samir Thakker vs Gadkari Builders and Associatesorder passed
CC00600000005656514/10/2018SHEETAL GADKARI, APARNA GADKARI vs M/s GADKARI BUILDERS AND ASSOCIATESorder passed
CC00600000008982022/06/2019Rajesh Tukaram Bhatkar vs Gadkari Builders and Associateorder passed
CC00600000019546431/12/2020Lekharaju Venkata Nagaraja Rao vs Gadkari Builders & Associatesorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Rera17632017Closed
Bombay High CourtWPL/41782018Ongoing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202530 Dec 2020Approval from MHADA pending
30 Jun 202531 Dec 2023We have faced many difficulties since the project started, Covid 19 , delay in approval from a government authority, financial problems, and because the project is expired in 2019
30 Jun 202530 Jun 20251. In 2020 due to the Pandemic situation of COVID-19 and the lockdown imposed by the government, we could not proceed with the construction activities. 2. Also, due to the pandem
31 Dec 201930 Dec 2025a. An explanatory note setting out the grounds and reasons for the delay in the completion of the real estate project 1. In 2020 due to the Pandemic situation of COVID-19 and the l

Location, Land & Connectivity

Located at Chembur, Subhash Nagar, Kurla, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by 13th Road, to the south by OB-12th Road, to the east by 40 wide Road and to the west by Semi Colon Pvt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport6 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district10 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Gadkari Builders & Associates is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Gadkari Builders & Associates

Gadkari Builders & Associates
FlaggedMumbai City

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Srushti Gagan
declared completion Sep 2023 · Chinnaiah Venkatesh Gowda
Srushti Garden
declared completion Sep 2023 · Chinnaiah Venkatesh Gowda
Srushti Kiran
declared completion Sep 2023 · Chinnaiah Venkatesh Gowda
Srushti Parivar
declared completion Sep 2023 · Chinnaiah Venkatesh Gowda
Srushti Raj Siddhi
possession by Dec 2027 · Chinnaiah Venkatesh Gowda
Srushti Vihar
declared completion Nov 2023 · Chinnaiah Venkatesh Gowda

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026